ISS Schedule Changes 05/23/01 vs. 06/27/01 (NASA ISS Felicity Report)

By SpaceRef Editor
July 10, 2001
Filed under , ,

  • Note: excerpt from the ISS Felicity Vol. 67 report, NASA JSC

    ISS Schedule Changes

    05/23/01 vs. 06/27/01

    Fligh
    Lev
    Schedule Item
    Change Since Last Felicity
    Reason
    Impact
    OA/ Program Office
    5P
    1
    LAUNCH
    1 Month

    New planning dates provided to OC by Russian Counterparts*

    TBD*
    4R
    1
    LAUNCH
    3 Weeks
    New planning dates provided to OC by Russian Counterparts*
    TBD*
    6P
    1
    LAUNCH
    2.25 Months
    New planning dates provided to OC by Russian Counterparts*
    TBD*
    OM/ International Partners
    4R
    1
    DC1/ CVM Ship to Baikonur
    1 Month
    Second Stage Testing between the DC1 and CVM was delayed due to lack of flight hardware. The test was completed using “test” hardware. Regression testing between DC1 and CVM using flight hardware will be required at Baikonur.

    No impact to 09/15/01 Launch Date. Current schedule provides four day window for regression testing with flight hardware, which is now available.
    OB/ Vehicle Prime Hardware
    9A
    1
    S1 Truss – RSI
    1.25 Months
    Resequenced to accommodate Installation of DDCU Coldplates & Ammonia Tanks & Regression Test prior to RSI.
    No Impact to Critical Path Tasks.
    11A
    1
    P1 Truss – RSI
    2.25 Months
    Resequenced to accommodate Installation of DDCU Coldplates & Ammonia Tanks & Regression Test prior to RSI.
    No Impact to Critical PathTasks.
    OB/Vehicle Non-prime
    7A. 1

    PEEK Phase II SAR
    1.75 Months
    Remanifested due to Delays of Sub- Components, Technical Problems and Cost Over runs
    Requires remanifesting to UF1; meets need date.
    10A
    1
    Node 2 O/ D
    1 Month
    Slip reported by Italians. Specific reason not provided.*
    Consumed one month of newly acquired 2.5 months of dwell (Interim Rev. F).*
    OD/ Avionics
    8A

    Stage DRs / Stage Verification – Complete
    1.5 Months
    6A Software Anomaly Resolutions
    Resolution near completion, patch being delivered within next week, which allows 8A work to resume.
    8A
    1
    Stage Ops IFL (9.0)
    1 Month
    6A Software Anomaly Resolutions
    Resolution near completion, patch being delivered within next week, which allows 8A work to resume.
    10A

    Stage Verif / Delta Verif – Complete
    15.25 Months
    Developed new schedule to synch up with new software deliveries and new launch date.*
    No impact. Verification still completed prior to launch date. *

    * – reason/impacts provided by owner