NASA Space Station On-Orbit Status 2 June 2019 – Cargo Transfer Completed
SpaceX-17 Dragon Status: Today the crew completed cargo transfer into the Dragon vehicle followed by a conference with ground teams.
Following cargo loading, the crew rotated the Common Berthing Mechanism (CBM) Controller Panel Assemblies (CPAs), installed CPA 4 and closed out the vestibule prior to egressing the vehicle. These activities are in preparation for Dragon departure tomorrow, June 3, at 11:00 AM CT.
Metal Oxide (METOX) Regeneration: The crew terminated round one of metox regen following the 14-hour cycle and initiated round 2.
Completed Task List Activities:
Friday
CSA “Ici La Terre” video, parts 1, 2
Photobioreactor troubleshooting (t/s)
RR12 Polar trash
SSC15 shell swap
EMU pump inlet filter found
Saturday
EMU ERCA t/s
Housekeeping procedure print
P/TV Lab SD camcorder swap
Ground Activities:
All activities are complete unless otherwise noted.
Cargo transfer ops support
Dragon egress and departure prep
Look Ahead:
Monday, 06/03 (GMT 154)
Payloads:
Capillary Structures
Furphy water transfer
Systems:
SpX-17 departure
MPEP removal
Veggie facility cleanup
Mouse habitat unit stowage
Tuesday, 06/03 (GMT 155)
Payloads:
Vascular Echo
ISS Experience
VEG-04 install
Systems:
71P departure
JEM grille cleaning
ISS surface/air sampling
Today’s Planned Activities:
All activities are complete unless otherwise noted.
Polar and TCU Transfer from ISS Overview
Polar Transfer To Dragon Overview Review
Cold Stowage Dragon Double Coldbag Pack Overview Review
JAXA Mouse Mission Item Gathering
Dragon Cable Routing
XF305 Camcorder Setup
JAXA Mouse Mission Post-mission Animal Transfer
Polar Transfer To Dragon Overview Review
Polar Express Rack Uninstall, Transfer, Handover And Dragon Install
Polar Express Rack Uninstall, Transfer And Handover
Furphy Procedure Review
Polar Express Rack Uninstall, Transfer, Handover And Dragon Install
Polar Express Rack Uninstall, Transfer And Handover
Cold Stowage Double Coldbag Pack
Cargo Transfer to Dragon
Cargo Transfer to Dragon
Dragon Locker Install
Polar Express Rack Uninstall, and Transfer, JAXA TCU Handover, and Polar and TCU Dragon Install
JAXA Mouse Mission Transportation Cage Unit Transfer to Dragon
Double Coldbag Transfer to Dragon
Metal Oxide (METOX) Regeneration Termination
Metal Oxide (METOX) Regeneration Initiation
Robotic Workstation (RWS) Setup
Node2 HD Camera Activation
Transfer Center Stack
Urine Processor Assembly (UPA) Brine Filter Changeout
PROFILAKTIKA-2. Hardware Setup
Recycle Tank Drain
Dragon Cargo Operations Conference
Recycle Tank Drain Part 2
Dragon Egress in Preparation for Departure
CBM CPA Rotation, Installation, and Closeout