EVA Hardware Board (EHB) Minutes of Meeting June 13, 2001
The EHB met at JSC on April 18June 13, 2001, in Building 1, Room 360, at 1:00 p.m. Representatives from the following organizations participated:
EHB Board members from the following organizations participated:
XA/Chairman, XA/Secretary, XA/Tools and Crew Aids, XA/EMU, XA/Integration and Operations, XA/TRI, EA/Engineering, EC5/EVA GFE, MV5/FCE, and NA/SR&QA.
The following items were presented:
- Hardware Integration Schedule XA/Barbara Counts
Changes to the schedule reflect the new launch date of 7/12/01 for STS-104 (7A).
- PRACA Status NS43/Terry Miller
Twelve A total of fifteen (15) FIARs are open for EVA hardware and are shown by flight as follows:
STS-100 (6A) 0
STS-104 (7A) 62
STS-105 (7A.1) 93
STS-108 (UF1) 14
STS-109 (HST) 15
Only new or major changes were reviewed as follows:
JSCEC0880 Top-Mounted and Side-Mounted WIFs. Top-Mounted WIFs Anodized surface is tacky and paint is flaking off. WIFs were fabricated by EM in April and hardware was inspected at that time for acceptance, which was rejected and returned, for rework. Hardware was recently returned for acceptance inspection with the same problems. Side-Mounted WIFs Anodized surface is tacky.
EC5/Kim Hostetler to have interim closure at 6/18/01 Tools Panel and final closure date.
No FIARs are open for STS-100.
STS-104 (7A) FIARs were statused as follows:
JSCEC0839 REBA Charger. REBA failed to show green LED during acceptance testing.
EC5/ Hiep Nguyen will be going to the contractor (Summit) 5/4/01.
JSCEC0863F Modular Gimbal Assy. End effector is sticking/not closing (STS-98 anomaly).
EC5/Roger Schwarz reported that he is getting more information from Oceaneering. There may be a "broke" in configuration control. Getting story.
BFCE026A024 High Strength Bridge Clamp. Unlock push button will not extend.
EC5/Roger Schwarz reported the hardware is going through vibe testing this week.
STS-105 (7A.1) FIARs were statused as follows:
BFCE029F105 Pistol Grip Tool (PGT). PGT Chatter.
EC5/Roger Schwarz reported this FIAR is still unexplained. The PGT will be shipped for MPLM Bench Review the end of the month. Interims will be written within the next 2 weeks. Hardware is to be left on-orbit.
The Chairman requested a note be added to the status to show dates interims are needed, shipping on open DR, etc.
The oldest FIAR, against the Adaptive Payload Carrier, is 589 645 days old.
- Certification Status NS22/Greg Wright
There were no updates to the Certification Status. A status on the hydrazine open certification will be presented to the 6/18/01 Tools Panel.
- EMU RDR and Certification Status NC512/Charles Sager
EMU RDRs open by flight are as follows:
STS-104 (7A) 1
STS-105 (7A.1) 7
STS-108 (UF1) 18
One new RDR was opened for STS-104 (7A). USA will generate a FIAR or DR to change the tracking number to USA and will have closure rationale for next weeks EHB.
There are four open certification items for STS-104 (7A). Paperwork on the EMU Middeck Battery Charger is with CTSD. Paperwork is being updated on the Protective Pouches and Protective Sizing Kit Cover. There is no open certification for STS-105 (7A.1). There are two open certification items for STS-108 (UF1). Athletic Support Assembly cert is pending crew input (Athletic Support Assembly vs. MAGs).
- On-Orbit Limited Life Status NA/Rod TolerRod Toler
The On-Orbit Limited Life Statusis to be presented the 2nd and 4th Wednesday of the month was deferred to the next regularly scheduled presentation on the 4th Wednesday. Copies of the presentation were distributed for EHB review.
- USA Limited Life Status USA/Nancy Jeanne Neason
- Funds Transfer Status XA/Janice Hall
The USA Limited Life Status was deferred to the next regularly scheduled presentation on the 4th Wednesday. Copies of the presentation were distributed for EHB review.
Additional funding for Sustaining Engineering ($600K) was transferred to EC on 6/12/01.
- EMU Rotation Plan (H7130) HSWL/Donna Ray
Revisions to the EMU Rotation Plan will be presented the last Wednesday of the month.
- USA SAFER Flight Logistics Plan (H-0933) XA/Anh Huynh
Revisions to the USA SAFER Flight Logistics Plan will be presented the last Wednesday of the month.
- IFA Status XA/Dale Roberts
IFAs were reviewed and statused as follows:
STS-92-7 PGT Chatter FIAR. USA/Scott Gorrell presented an updated status on the PGT Chatter FIAR as follows:
- PGT S/N 1003 has been sent to Swales to undergo 1G ambient testing similar to the testing performed on PGT S/N 1005 to reproduce the anomaly.
- Thermal, vacuum, and EMI testing will not be performed at this tie.
- Thermal, vacuum, and EMI testing have been performed as a part of the PDA.
- Subsequent use of the PGT during the EVA would indicate that these factors were not the cause of the anomaly.
Testing should be complete by Friday, 6/15/01. Three to 4 weeks will be required if refurbishment is needed. Test results will be E-mailed to XA/Dale Roberts.
- EHB Actions Status XA/Dale Roberts
- H7150 FEMU-R-001 Updates to Include Bladder Crease Inspection ILC/Mike Pantaleano
- H7158 FEMU-R-001 Corrections and Updates HSMS/Colin Campbell
This item was deferred.
This CCBD requests updating the FEMU-R-001 to screen for creasing of the glove bladder after wrist disconnect flange assembly. This is corrective action for RDR 1-EMU-106-011.
Decision: Approve.
This CCBD requests updating the FEMU-R-001 to correct typographical errors and incorrect specification references that do not comply with the PLSS/SAD. In addition, this CCBD provides FEMU-R-001 changes that are needed to address processing for 7A.1 (helmet fitcheck) and improve hardware processing. It further revises ground usage of the CCC to prevent usage beyond capacity. It will also incorporate additional requirements into FEMU-R-001 to make it comply with various PLSS S/AD test notes.
Decision: Hold pending decision of the Manager, EVA Project Office, on the CCC chamber reuse.
No further items were brought forward, and the EHB adjourned.
Submitted by: Approved by:
(Original signed by) (Original signed by)
___________________________ ____________________________
Harriett Attaway Brian Johnson Dale R. Roberts
EHB Secretary Acting Acting EHB Chairman