Status Report

Alpha Health and Status Report 16 June 2001

By SpaceRef Editor
June 16, 2001
Filed under , ,









The 8 O’clock Report


Alpha Health & Status


June 16, 2001 (GMT 167/00:00)


(The information highlighted in blue is update to yesterday’s report)



Overall Alpha System Status:
















ELECTRICAL POWER GROUP (EPG)



Russian Segment:


  • FGB Batteries- Incomplete Charge Mode

  • FGB Battery 3 in cycle mode

  • FGB battery 1 OFF

  • FGB RACU-6 is ON

  • SM Batteries – Incomplete Charge Mode

  • SM ARCU 23 ON

  • SM Batteries in Incomplete Charge Mode

  • SM Battery 6 Off


USOS:


  • Both channels fully operational

  • BGA 2B and 4B in Rate Mode

  • PCU 1 in Standby; PCU 2 in Discharge

 


ENVIRONMENTAL CONTROL GROUP (ECG)



Russian Segment:


  • Vozdukh – ON

  • Elektron — OFF

  • CKB-1 – OFF

  • [CPBK] – ON

  • БМП – On purification

Air Duct ПХО – ON


Air Duct ПРК — ON


  • RSOS Smoke detectors

  • SM – ALL NOMINAL

  • FGB All Nominal

Node1:


  • Cabin Fan – On

  • Aft Port IMV Fan ON

  • Aft Port, Fwd Port & Stbd IMV valves Open

  • SD-1 Enabled

  • SD-2 — Enabled, recovered

  • Stbd Hatch PPRV CAPPED

  • Cabin Pressure FDIR – Inhibited

  • FWD, AFT Hatches open

  • RAMV — Enabled

USL:


  • PCA: LAB PCA in Monitor, PPR Enabled

  • Rapid depress FDIR Enabled

  • IMV: AFT Valves open;

  • Aft Port Fan – ON;

  • Fwd Stbd Vlv – CLOSED;

  • Fwd Stbd Fan – OFF;

  • SD-PD1 Enabled

  • SD-D6 Enabled

  • SD-SD5 Enabled

  • SD-D4 Enabled

  • ARS: MCA is in IDLE – pump out required

  • LAB1S6 CCAA is off.

  • LAB1P6 CCAA is on.

  • CDRA-OFF (State-Failed)

  • D6 AAA-ON;

  • D4 AAA-ON

  • WRM: Initialized No Vent State

  • VS-VES – VES Inhibited & Vent vlv Closed


  • VS-VRS – VRS Inhibited & Vent vlv Closed

  • TCCS — ON

  • Aft Hatch Open

Payload Racks:


  • LAB1O2 AAA ON, SD Enabled

  • LAB1O1 AAA ON, SD Enabled

  • LAB1S2 AAA Off, SD Inhibited

 


 


 


Crew Support Group (CSG)



  • SSC 6A Network Reconfiguration complete

  • MACE Silo 1 test & checkout complete


Motion Control Group (MCG)



  • Att Control Mode: Thrusters Attitude Hold

  • Attitude: TEA is LVLH

[0, (-10),0]



THERMAL CONTROL GROUP (TCG)


Russian Segment:


  • FGB external loop НГК 1 ON


  • FGB BГK P3H4 ON

  • SM КОБ 1 Panel 2 – ON (3СПН2 PUMPS 1&2 ON)

  • KOX1 — OFF


 


USOS:


  • EETCS Loops A & B running on A pumps with FCV control enabled.

  • EETCS Loop A and B PFCS Line Heater 1 & 2 CLC Enabled.

  • IATCS is in Dual Mode with elevated LTL set-point.


COMMAND AND DATA GROUP (CDG)



Russian Segment:


  • ЦВМ: ЦВМ 1 Operating, 2 & 3 OFF

  • [ТВМ]: 1 Operating. [ТВМ]-3 dropped out of the set @GMT 066/04:52:47 [ТВМ]-2 dropped out @ GMT162/15:50

  • FGB MDM: FGB-2 ON/FGB-1 Off

USOS:


  • C&C3: primary (7A config), C&C1: backup (7A config), C&C2: Standby (7A config)


  • INT: INT-1 Operating/INT-2 OFF

  • N1-2 Primary/N1-1 Secondary

  • PV MDM: 4B Prime/2B Wait

  • GNC: GNC-2 Primary/GN&C-1 Backup

  • LA: LA-1, LA-2 & LA-3 operating

  • PMCU: PMCU-1 Operating/PMCU-2 OFF

  • PL: PL-1 Operating/ PL/CC MDM in PL-2 slot

  • APS-1, APS-2, PEHG-1 Operating

  • PEHG-2 off


COMMUNICATIONS AND TRACKING GROUP (CTG)



Russian Segment:


  • Komparus IFM activities have been completed and system checkout activities from MCC-M are continuing.

USOS:


  • S-Band is operating nominally in High Data Rate Mode.

  • Audio System performance is nominal.

  • Video Subsystem performance is nominal.

  • Ku-band is operating nominal with the auto track software patch in use.








 


MAINTENANCE AND REPAIR GROUP (MRG)



Completed Maintenance Tasks:


Russian Segment:


·
FGB Smoke Detectors 1,3,4 & 5 replaced.


  • SM Battery — 2 Changed out and functioning


USOS

Designated Maintenance Items (DMIs):



Russian Segment:


·
SM ПТАБ —6: Failed — Battery 2 inserted, slot 6 is Nonfunctional



USOS:


Node 1


·
P/TV—Hasselblad Camera

USL


·
AR Rack CDRA:


– Sorbent Bed


·
AR Rack MCA:

– Mass Spectrometer Analyzer



    • Data Control Assembly

CSA:


·
SSRMS


– Base LEE Camera Light


Assembly




STRUCTURES AND MECHANISM GROUP (SMG)



  • Lab Cradle Assembly (LCA) Heaters 1 & 2 Enabled

Completed S&M Tasks:


  • ELPS NOD1P1/P4 installed

 


ROBOTICS



CUP RWS – Active


LAB RWS – Backup


SSRMS Prime String – Off


SSRMS Redundant String – Operational

The Redundant String will be left Operational overnight for troubleshooting purposes.



 


Visiting Vehicles:



  • 2S docked on FGB Nadir

  • Progress 4 docked SM Aft

Last 24 Hour activities:

ISS Crew


  • Med Ops — Blood Testing [Complete]

  • MACE II Ops

  • O2 repress from Progress (If needed) [Deferred]

  • SM Battery 2 and 6 Swap

  • SSRMS Operations [In Work]

  • PAYLOADS *


  • DOSMAP MDU Start Charge

  • Daily status checks


  • Task List (may be done at any convenient time)

    1. Exercise file Download

    2. PERS Video D/L

    3. Earth Obs

    4. 6A transfer questions

    5. Bar Code Reader Fam

    6. Node K bar Install


* Payload activities involving Crew interaction. Other payloads are untended (except status checks) and not listed here.



Upcoming Events at a Glance:



  • Flight 7A launch has been rescheduled for no earlier than July 7th (between July 2-8) and Flight 7A.1 NET August 5th. Special meetings continue to discuss options.


Trajectory Status

Time: 06/15/01 166/12:30:00 GMT


  • Ha x Hp: 396 x 368 km

  • Have: 382 km

  • Beta Angle: 24 deg (magnitude decreasing)

  • Decay Rate: ~300 meters/day

Non-Prop Consumables (US-Calculated values) as of Friday 06-15-01:



 





















































Item


Remaining


Predicted Rate


Contingency Redline [a]


Margin


ТГК canisters


160


3 units/day/3 crew


135


8 days


Oxygen Gas


0 lbm


5.3 lbm/day/3 crew


N/A [b]



0 days


Russian LiOH


15


1.04 cans/day/3 crew


9 [b]


13 days


US LiOH


19


1.50 cans/day/3 crew


9 [b] 


Potable water


2091 lbm


6 lbm/day/3 crew [c]


270 lbm [c]


303 days [c]


Technical water


1336 lbm


8.6 lbm/day/3 crew [c]


387 lbm [c]


110 days [c]


USOS Condensate


104 lbm





(a) Basic 45 Day Skip Cycle Requirement.


(b) Skip cycle requirement exemption due to availability of spare parts for Elektron and Vozdukh. Basic requirement of 15 days of LiOH capability.

(c) Remaining quantity is based on reported on-orbit water, on predicted usage rate, and on performance of water reclamation systems. The water usage rates used in predicting on-orbit Nominal Capability are documented in ISS-4A / STS-97 CHIT 211 but are under assessment for revision. The current totals do not include 463 lbs of Rodnik water (Potable), 79 lbs of RS Condensate (Technical) and 102 lbs of EDV water (Unknown).


Propulsive Consumables as of 06-14-01



























































 


Current Altitude:


384


km


135 Day Alt:


298


km


Total FGB Prop Avail


2841


kg


Total SM Prop Avail


764


kg


Total Progress Prop Avail


856


kg


Total Prop Avail


4461


kg

Skip Cycle Prop



80


kg


Priority 1&2 Prop


73


kg

Skip Cycle Margin



4381


kg


Priority 1&2 Margin


4388


kg

Lifetime



448


days











































































Priority 1 Propellant


Next Docking Attempt


33


Shuttle


5


 


Progress


33


 


135 Days to 150 nmi


0


135 Days of Att Cntl


0


1 m/s COLA burn


35


 


 


Total Priority 1 Prop


68


Priority 2 Propellant


Altitude Maintenance


0


Attitude Control


0


Shuttle Docking


5


Total Priority 2 Prop


5


Priority 3 Propellant


Skip Cycle


1175


 


Adj. Skip Cycle


80


 


Total Priority 3 Prop


0


Priority 4 Propellant


Science Budget


 


0


Open Items for Investigation (IFIs)


(IFI status will be updated every Monday and changes will be reflected on Tuesday’s report in highlighted blue. Newly opened IFIs will be reported on daily basis in highlighted blue)

 


  COMMAND AND DATA GROUP (CDG)



  • C&DH – (MER-0368)- C&C 3 MSD Inaccessible

During 6A on GMT 119/19:08:50, C&C3 was moded into Primary in response to a number of "MSD Inaccessible" flags being received from C&C2. C&C3 later malfunctioned, dropping telemetry and communication with the ISS. C&C2 was later brought up as primary. The C&C3 MSD was changed out and has been fully operational since. Investigation continues.


.


  • C&DH – (MER-0408) — PCS Reboots and Disconnects

Crew Reports that both PCS’ they are using have occasional spontaneous reboots and disconnects from the bus. PCS Log files have been dumped and are being analyzed by PCS team. CHIT ISS-0305 has been opened. Investigation continues.



  • C&DH – (MER-0416) — N1-1 MDM Power Cycle

ODIN completed load of INTSYS version 39 software to INT-1 MDM, then transitioned INT-2 to standby in preparation to bring INT-1 on as primary. While both INTs were in standby, a loss of comm with N1-1 was reported by N1-2 and CCS. N1-2 performed a power cycle of N1-1 and N1-1 returned to a nominal state as secondary node MDM. INT-1 is operating nominally with INTSYS version 39. INT-2 is in standby with version 38 still loaded. Several RPC’s appear to have changed states during this event. Investigation Continues.



  • C&DH – (MER-0424) — Payload MDM PAR PLMMDM1-SW-0005

Under Investigation.



  • C&DH – (MER-0432) — PL MDM Crash

Under Investigation.

 

ELECTRICAL POWER GROUP (EPG)



  • EPS- (MER-0326) – High resistance on SM Solar Array Generator #3 Power Cable

The SM Power specialists reported that after analyzing the data obtained during the SM Solar Array Generator test on GMT 2001/093, they suspect that some cables or a part of the solar array/current regulator circuitry may be damaged. This assessment is PRELIMINARY. They will have to further analyze the data and possibly perform more tests to have a complete understanding of the problem. More data will be available as the SM power specialists provide it.


Significance to vehicle: Degraded power production capability in the SM.


Significance to operation: The degree of degradation has not been determined yet, but is not currently impacting SM nominal operations. Further investigation is underway by the Russians. Closure is currently under evaluation for the Russian Anomaly.



  • EPS — (MER-0405) – PCU Abnormal Transition to Shut Down Mode

On GMT 138/0603, PCU1 was transitioned from Standby with tubes at ~0mmHg to Shutdown. The process was expected to take 4-5 hours, as Latch Valve 1 Closes, Latch 2 Opens, and the gas between (initially at tank pressure) needs to bleed down to less than 1400mmHg (27PSI) before Latch Valve 2 Re-Closes. The expected tube pressure profile was that the pressure would remain at 2500mmHg (50PSI) for roughly 4 hours, then the pressure would exponentially decay to 0mmHg. Latch Valve 1 closed as expected and telemetry confirmed. Latch Valve2 opened, but closed within 10 seconds; the downstream pressure increased to ~2000mmHg (39PSI) confirming the valve did open, but we did not get telemetry feedback that the valve had opened (0.1Hz Tlm). Additionally, the ~2000mmHg was not the expected pressure, as the regulator regulates to approximately 2500mmHg (50PSI). The pressure began the exponential drop to 0 immediately. Analysis of the firmware shows that during the shutdown routine, valve 2 is commanded open, and the line pressure is checked immediately after. The valve has not had sufficient time to open, and therefore the pressure is less than the 27PSI set point. The valve is then commanded closed, without depressurizing the line between the two valves If it is desired to depressurize the line between the two valves, then the following procedure may be used: Command the PCU into Manual Mode, command valve 2 open, wait until the pressure drops below 27 PSI, then reclose valve 2. Power may then be removed from the PCU, or it may be recommended into Shutdown Mode. Safety to recommend a PRACA or a Firmware PR for this issue. Firmware does not properly execute the shutdown function. This is considered a known condition with an operational workaround.



  • EPS — (MER-0423) – SM ZRU (EPS String) #6 Failure

On GMT 140 Russian EPS specialists noticed that the SM Battery 6 had stopped charging and discharging, so they disconnected ZRU #6. Troubleshooting repeated the problem on GMT 144:17:52. Russian EPS specialists believe the PTAB #6 has failed and will need to be replaced. Investigation continues.

VEHICLE INTEGRATION (VI)


  • VI — (MER-0335) – MCA Error Code 33

At GMT 2001/104:10:43:39, a Zero Cal of the MCA was initiated. It was completed at GMT 2001/104:11:01:59. Subsequent to the Zero Cal and during a break in data between GMT 2001/104:11:09:35 and GMT 2001/104:11:11:009:55, the MCA failed passive BIT Filament (Error Code 33). This condition sends the MCA to STOP with an automatic restart. The MCA performed a successful Active BIT during STARTUP and came up to STANDBY. MOD dumped the MCA data associated with this and it looked fine (No FAIL indication; No C&W indication). BIT Fault data showed nothing. MOD placed the MCA back to OPERATE and it performed satisfactorily. This incident occurred when the Station was away from the South Atlantic Anomaly but during a period of high solar activity. Orbital Science (vendor for the MCA) reported that in the MCA ORU 2 (the MCA part of the MCA) there is a voltage/frequency converter that has a slight susceptibility to EMI. Orbital is concerned that this item may be the reason for the problems experienced by that ORU.

Occurred again at GMT 113/08:07. Same Signature, same status changes. Same nominal start-up after. High Solar activity also noted at this time.

Occurred again at GMT 114/18:55. Similar signature. This caused Brief shutdown of U.S. Element capability to measure O2, N2, CO2, H2O, H2, and CH4. 06/30/01: Plan is to replace MCA electrometer and electronics unit This addresses both problems (MCA electrometer saturation and EMI problems thought to have caused MCA shutdowns). Problem is believed to be leakage through swaged joints on FRIT (flow restrictor). MCA currently operating nominally on filament #2. Indications are that trend toward saturation has slowed significantly, perhaps stopped. Cause of problem either:


  1. Software thinking it has a problem with the filament (caused by EMI, South Atlantic Anomaly or solar flares).


(2) The buildup of oxidized metal in the ion pump; periodically flakes of this oxidized metal will break off and float into the ion beam and cause a reading that exceeds the limit and causes the MCA to shutdown.

For Cause (1) above, the solution would be to change the ion pump current limit.

For Cause (2) above, the solution would be a design change of a circuit card and a change out of the ORU. PRACA PR# 2681 has been generated.



  • VI — (MER-0386) — FOD in CPA Connectors


Report from 6A crew debrief:

When reinstalling the Nadir CPAs, specifically when removing the caps from the cable or CPA connectors (they don’t remember which), they noted at least two “EMI tabs” floated out of the connectors. These were very small (1 – 2 mm across) C-shaped pieces of metal. Crew thought they were broken off from an EMI-ring that goes on every connector (?). They captured two, put them on a piece of tape, photographed them, and put them in the “Lost & Found” zip lock bag. No operational impact, possible safety impact during demate due to FOD. Crew should wear eye protection during cable demate. PRACA #2702 has been generated.



  • VI – (MER-0381) – PVCA Numeric Constraint – Invalid Orbit Elapsed Time

On 127/06:38, a Numeric Constraint C&W was set. Data dump of the C&W associated data revealed the following:

5/7/01: The Numeric Constraint bits indicated two procedures have triggered the Numeric Constraint since the last time the associated data was reset. The two are Cmd Validation and Orbit Elapse Time. The Cmd Validation is an expected cause whenever a beta angle of 359.99- 360.00 is sent to the BGA (SPN 18844/1112). The second one has not been seen before. It occurs and is handled within the Determine Orbit Elapse Time procedure. No other algorithms are skipped at a result of this Numeric Constraint. The cause of the problem is tied to the Orbit Elapse Time holding at 6000 for a long time. If the difference between the current time and the Internal Base Start Time (what PVCA believes is the last sunrise) is greater than the defined type range (duration type, S18F14), the error will occur. The largest value the type would hold is 131,072 which is almost 22 orbits. Preliminary data shows the Orbit Elapse Time has been stuck at 6000 for about 24 hours. The Numeric Constraint will stop occurring when the Orbit Elapse Time resets to zero. The Last Orbit Targets Blind mode may not operate correctly, due to the Orbit Elapsed Time It is advisable to not use Autotrack BGA Mode, as the corresponding Blind Mode may not work. clock not counting correctly. It was recommended to PHALCON to place the 2B array in Rate Mode (was in Autotrack) and change the blind mode to Rate. 4B is in Directed Position, which is OK. Investigation:


5/8/01: Data dumps of various locations in the PVCA Memory were performed to give details of the Orbit Elapsed Time function:


5/9/01:

1) The data dumped from PVCUs confirm that the Base Start Time used in the Orbit Elapsed Time calculation is not getting updated properly. The last rise acknowledged by the Orbit Elapsed Time (OET)


calculation was May 5 18:15:14. The calculated (once a second) difference between the Base Start Time and current time is causing the persistent numeric constraint error.

2) The Rise and Set time appear to be updating correctly. Although, a comparison of ODRC values for


Rise/Set from GNC/C&C do not match Rise/Set values dumped from PVCU. They are off by 15 and 23 seconds, respectively. Very puzzling. However, since the Rise and Set times are updating, we can conclude that the Sunlight Status is correctly being determined. Only the Orbit Elapse Time (and those that use it) is affected.


  1. The dump of the backup PVCU provided similar data. Both set of dumped data indicated the dumps occurred after a sunrise and before a sunset. Of note is a two second difference between the Rise time saved (and supplied via BAD) and that of the internally saved Next Orbit Start Time (NOST). The Rise time was later than the NOST. This would not cause a problem.


  2. If the Rise time was earlier than the NOST, then when Rise time is passed the NOST would be updated. This would occur before the NOST was moved into the Base Start Time and effectively move the orbit rollover time further out (OET stuck at 6000). If this happened again and again each orbit, the OET will be at 6000 for multiple orbits. Note: On April 30, OET was stuck at 6000 for one orbit and then self corrected. We have not been able to find data to support getting from statement (3) to statement (4). The ODRC data show steady Rise Times, no Rise time fluctuations of a second or two after Set time and before the Rise time.

5/10/01: A continuous data dump of the memory locations is being requested to watch the data over two orbits. CHIT 7A-ISS0050 was written to give MOD a procedure to clear the Numeric Constraint Flag and provide advance warning should the same conditions occur that would cause the flag to be set again. CHIT was performed on GMT Day 158, and the Numeric Constraint Flag was successfully cleared.



  • VI – (MER-0433) – Debris in MPLM IVA Volume

STS-102 crew reported seeing “lots of small bits of foil floating” inside FM-1 MPLM on ingress. When the MPLM was inspected on de-integration at KSC, a significant amount of debris was observed covering the Air Return Grid (ARG) screen filters. The particles, ranging in size from 1 to 1900 microns, were found to be 30% metallic, 18% organic, 45% organic fiber, and 7% miscellaneous. The fraction of metallic particles is in excess of that found from debris collected after Spacelab missions.

During STS-100, the crew again reported seeing metallic particulate inside FM-2 MPLM on ingress. Upon to return to KSC, ARG screens were again sampled. The amount of particulate was less than for STS-102, but the metallic particle fraction of the contaminant was 45%. The metallic particulate was mostly aluminum for STS-102, and all aluminum for STS-100.

During debriefing, after returning from the ISS, the STS-102 Crew described seeing "lots of small foil floating" inside the FM-1 MPLM on ingress. When the MPLM’s Hatch was opened at KSC an abundance of debris was observed covering the Air Return Grid (ARG) Screen Filters. A PR was taken and all eight (8) screens were cleaned using a flight vacuum fitted with a new filter. Note: these screens were cleaned before M&P visually inspected them but digital images were taken and are on file. The collected debris was submitted to the NASA Lab for analysis to determine its composition.

Results of the Lab’s analysis showed the composition of the debris to be: metallic (30%), red (1%), white (5%), black (1%), white clear (T), amber (T), green (T) and blue (T) materials, along with organic (18%), and organic fiber (45%). The metallic particulate consisted mainly of aluminum alloy. Note: the specific aluminum alloys (6061, 7075, etc.) were not defined. The red materials were composed of RTV and primer. Green and blue materials were paint chips. The black material was composed of 1) carbon steel corrosion products, 2) calcium-chlorine-silica-carbon rich, and 3) molybdenum-sulfur rich materials. White and white clear materials included paint chips, aluminum-chlorine-silica rich and calcium-silica rich materials. The amber materials were made up of aluminum-oxygen rich materials. The particle sizes ranged from 1 to 1900 micrometers.



Debris was also observed on the duel Hatch Seals. It was collected and analyzed to determine its’ composition. Results showed it to be comprised of basically the same components as debris cleaned from the ARG Screen Filters.

Note: a comparison of FM-1 MPLM debris’ composition was consistent with the analysis of debris collected from Space-Lab missions. The only exception being the percentage of metallic particulate. This could be attributed to the last minute work done inside the MPLM installing Racks’ knee braces.

During STS-100 the crew reported also reported seeing metallic particulate inside FM-2 MPLM. Upon return to KSC, M&P performed a visual examination of FM-2’s ARG Screen Filters during ingress. FM-2’s ARG Screen Filters appeared to be similar, though not as dirty, as what was witnessed in the FM-1’s digital images. Another point of interest was the four (4) ARG Screen Filters, adjacent to the install two (2) RSR Racks, contained more debris than the four (4) ARG Screen Filters located by empty bays.

After examination, all eight (8) of FM-2’s ARG Screen Filters were cleaned and the collected debris analyzed like in FM-1. The results were basically the same with the exception being that the percentage of metallic contamination was higher (Ref. 45% vs. 30%) and organic contaminants lower (Ref. 45% vs. 63%) than in FM-1.

An inspection and contamination analysis was also preformed on debris collected from the RSR Racks currently installed in FM-1 for STS-105. All the collected metal particulate sampled turned out to be aluminum alloy. The rest of the debris consisted of black Molybdenum-sulfur rich materials (i.e. dry lube), gray silica-calcium rich materials and yellow paint particles.

All of the samples mentioned above are in M&P’s possession if needed for further analysis. Copies of all NASA Lab analysis are available upon request.

Some potential sources for the contamination found inside the MPLM’s could be:


? Migration into the modules from inside installed RSP, RSR, and Express Racks


? Transfer into modules on orbit from ISS elements/environment


? Present inside the modules from the original fabrication


? Generated during Rack modification &/or routine processing inside the modules


? Created during GSE floor installation/removal


? Migrating in on protective padding, personnel, other GSE


? Coming in from rotation stands/RID during rack installation


? Created by Rack installation/removal during ground processing or on orbit

To my knowledge M&P was never involved in a "base line" cleanliness inspection inside FM-1 or FM-2 MPLM. It should be also be noted that M&P Engineering was not included in the closeout inspection process of neither MPLM’s internal bays nor the installed Racks on STS-102 or STS100 missions.

Due to the contamination concerns, KSC M&P Engineering has implemented a weekly OMI R6900 cleaning inside FM-1 Module. This has already made a noticeable difference in the cleanliness level inside the MPLM. We’ll do the same for FM-2 after de-integration is completed. We’ve also asked that cognizant Systems Engineers included us in the closeout inspection process on internal bay and Racks. Investigation Continues.

 

MOTION CONTROL GROUP (MCG)


  • GN&C – (MER-0399) — SM-Y (Nadir) Kurs Test Failure

Same problem as IFI MER-253 and PRACA 2634. Exp 1 did some cable re-config to disconnect the SM Kurs-P avionics box from the SM forward port (to support FGB-SM docking) and connect it to the SM nadir port (to support DC1 and UDM dockings). Initial self-tests showed a failure of one Kurs set (led to IFI MER-0253 and PRACA 2634). They tried adjusting and re-tightening several connectors, but still saw failure of one set. Additional troubleshooting indicated a bad cable, so the Russians sent up a replacement cable on Progress 4P.

Exp 2 replaced the cable, but then both Kurs sets began to fail the self-tests (led to IFI MER-0399). They tried adjusting and re-tightening several connectors, but still saw failure of both sets. Additional analysis by the Kurs specialists indicated a bad cable configuration left over from previous testing. The crew connected the proper Kurs-P 4AO antenna to the Kurs-P avionics box on 6/6. A Kurs self-test on 6/7 had successful results, with both sets passing the self-test. This IFI Under Investigation.



  • PROP – (MER-0430) — Progress Thruster Firing Anomaly

HSG reported that all went well with manifold 2 but there were problems with manifold 1, either an over or under pressure in the thrusters caused them to shut down and automatically hand over to the SM thrusters. Investigation of this problem continues. SM thrusters will be used for now.

 


ENVIRONMENTAL CONTROL GROUP (ECG)



  • ECLSS – (MER-0316)- Elektron Unexpected Shutdown.

The Russians reported that the problem was the Elektron power supply (power cable). They reported that they would command reactivation during their next ground pass; they expected this to be successful; if not successful, there is a spare power cable onboard. At GMT 2001/088:06:41:16, the Elektron Fail indication was reset. During an LOS between GMT 2001/088:13:06 and GMT 2001/088:13:22, the Elektron was deactivated (the Progress vehicle was available for Oxygen supply). As of GMT 2001/102:14:30:00, the Elektron has been operating satisfactorily for several days.


Message sent to MER Moscow requesting part number and serial number. This IFI is under evaluation for closure.



  • ECLSS – (MER-0319)- High Cadmium Levels in Water

Water samples taken from the SVO-ZV crew ambient water dispenser on Flight 4A exceeded the SMAC levels for cadmium. Samples taken on 5A.1 were lower than the 4A samples but exceeded SMAC levels. Potable water source is contaminated with cadmium. Source of cadmium was determined by the Russians to be the dispenser that flows from the SVO-ZV to the crews drinking water. The dispenser contained cadmium, which was released into the water as it was dispensed. Russians have plans in place to remove the dispenser and use the SRVK sample adapter to hook up to the SVO-ZV to dispense water. This sample adapter has been used for previous sampling and has shown to not contaminate the samples with cadmium. Source of contamination has been found and an on-orbit workaround has been developed to prevent continual contamination. It is recommended that a PRACA (need P/N and S/N) be opened for this problem, and the IFI can be closed to the PRACA when repairs have been made and another water sample proves that the cadmium source has been removed. PRACA PR# 2643 has been generated to track this problem. Subsequently, a MAR (ECLSS-00016-BASIC) has been issued to manifest the repair parts.



  • ECLSS – (MER-0328)- SM BB2PO Fan Failure

Crew reported the BB2PO fan failure at GMT 2001/94:20:29. The crew removed and inspected the fan. One of the fan blades was damaged. A 2.5 cm piece of debris was found in the vicinity of the fan when inspected. The debris is the most probable cause of the failure. Significance to vehicle: Loss of fan until replaced with another MO-1-5006 fan. Significance to ops: Crew is currently taking the BTK2 fan in the SM and installing it in the place of the failed BB2PO. A 2.5 cm piece of debris was found in the vicinity of the fan when inspected. The debris is the most probable cause of the failure. Fan has been replaced and is operating satisfactorily. To completely restore normal operations, a replacement fan for the BTK2 fan in the CKB2 side of the ventilation system. It is recommended that a PRACA be opened for this problem. P/N and S/N requested from MER Moscow on GMT 2001/150.



  • ECLSS – (MER-0339)- MCA Error Code 33 with INT Stop Cmd

John Carr (ECLS) reported the following: Error Code 33 occurred again. MCA went to RESTART. RESTART did not work. For some reason currently not understood, the INT sent a STOP command to the MCA and the MCA went to IDLE. MOD sent a STARTUP NORMAL command and the MCA went to OPEARATE with RAPID SAMPLING of the Lab (MOD did not want the MCA to lose its vacuum.). While in OPERATE, the MCA Location Accessible parameter went from YES to NO. At that time MOD commanded the MCA to STANDBY. The incident appears similar to the incident of last Saturday (GMT day 2001/104) except for the STOP command from the INT and the Location Accessible indicating NO. Problem caused by either:


  1. Software thinking it has a problem with the filament (caused by EMI, South Atlantic Anomaly or solar flares).

  2. The buildup of oxidized metal in the ion pump; periodically flakes of this oxidized metal will break off and float into the ion beam and cause a reading that exceeds the limit and causes the MCA to shutdown.

Proposed solution – for cause (1) above, the solution would be to change the ion pump current limit. For cause (2) above, the solution would be a design change of a circuit card and a change out of the ORU. PRACA PR# 2682 has been generated. S/N#F0002.



  • ECLSS – (MER-0348)- VRS Leak rate higher than expected

During 5A.1 with VRS Vent Valve open, VRS System Pressure was approximately 250 microtorr. This is significantly higher than was observed on 5A. After closing VRS Vent Valve, VRS pressure rise rate was observed to be approximately 218 millitorr/hour. (This compares to a pressure rise rate of approximately 1.86 millitorr/hour after VRS Vent Valve closure during 5A). The "spec" leakage rate for the VRS is 4 x 10exp-4 scc/second. With the spec leakage rate, the VRS System Pressure would rise at a rate of approximately 18.6 millitorr/hour. Pressure rise rate data suggests the VRS was leak-tight during 5A, but may now be leaking. Pressure rise rate of 218 millitorr/hour is roughly consistent with a leakage rate, which would produce 250-microtorr pressures at the VRS CCT with the Vent Valve open. When crew time available (e.g., during 6A stage) disconnect HRF Payload from VRS and cap the VRS QD at this location. Observe whether this eliminates the leak. There is no urgency to do this. There are no payloads, which need to use the VRS through at least 8A. (Although we should do this as soon as conveniently feasible, since if HRF is not the problem, we will have more time to resolve the problem).



  • ECLSS – (MER-0427)- Node 1 Smoke Detector Obscuration and Scatter High

Under Investigation.



  • ECLSS – (MER-0428)- MCA Purge Time Override Failure and Loss of Synchronization with the INT MDM

Under Investigation.



  • ECLSS – (MER-0429)- Leaking CWCs

Under Investigation.

 


COMMUNICATIONS AND TRACKING GROUP (CTG)



  • C&T — (MER-0259) – Echo on S Band (Ground).

When CAPCOM is talking to the crew in the SM, the ground hears an echo. The ground hears a repeat of their voice. The ISS audio system was configured with S/G 1, ATU Lab 1, ATU Lab2, and RSA 1 in Public Loop1 and S/G 2 ATU Lab 1, ATU Lab 2, and RSA 2 in Public 2. It is probable that the SM audio system was configured in a way that the voice was looped back down the S/G channel.


Forward plan for closure:

OCA_1578 US/RS Comm Configuration procedure was uplinked to the crew to give them an integrated audio config procedure and integrated audio diagram to help them understand the system better. CATO believes that the audio echo is a product of how the RSA1 and 2 lines are connected to SM comm panel 3 and 2 respectively. CATO also wrote OCA 1652 — S-band Troubleshooting. The crew due to a full timeline has not performed it. It will be performed post 5A.1. C&T will write a Chit for on board troubleshooting. Investigation continues.



  • C&T — (MER-0329)- VBSP Channel #4 Configuration did not go to Default

The VBSP went to self test when commanded to equipment self test, and the equipment self test status was active, Self test was terminated by issuing a deactivate equipment self test command. Upon termination equipment self test, the VBSP did not go to default configuration because it did not start in its default configuration (when the correct self test command is sent to the VBSP, it is expected to return to its default configuration). Currently, the command sent to initiate the VBSP self test command is INCORRECT (see PR15876). In all of our testing, we always ran the self test right after the box was initially powered up – i.e. started in the default configuration, and when it was sent the deactivate equipment self test command, it just returned to where it started. We suspect that’s all it’s doing now returning to the state it started in.

We believe this IFI should be closed because the software will be fixed at Flt 8A with the CCSR2 load. We could probably do some investigative testing at ISIL with the DVTM but we don’t believe that’s really worthwhile because we have a debugging plan referenced above, and the s/w will be fixed at Flt 8A and this won’t be an issue anymore.



  • C&T — (MER-0333)- MCOR (Medium Rate Comm. Outage Recorder) Upper Temperature Accidence.

When MCOR Activation & Check-out procedure was being performed; on step 7, MCOR had to shutdown due to over temp. MCOR was activated at approx. 101:23:02GMT (6:23 pm CST??). Two minutes later we received heartbeat indication.

Steps 1-6 were completed from the procedures flawlessly. Commands accepted, RT enabled, verification of default configuration and health, documented memory configuration, initiation of BIT test and verification of BIT results. At the step 7 (enabling recording of input channels 4 and 8), the overtemp indication flag came up and MCOR had to shutdown. It happened approximately 45 minutes after activation. Investigation continues. ART will come up with the rational to close this IFI ECD 6/08/2001.



  • C&T – (MER-0355) — Broken ECOMM Connector

The Early Communication System (EComm or ECS) Starboard Antenna was removed during the 6A EVA2. When the EComm data and power cables were disconnected, part or parts came loose from the cable connectors and floated away. One or more part(s) moved towards the CBM. [IFI 0352 was written to investigate, track, and resolve the Foreign Object or Debris (FOD) situation.] (The EComm Starboard Antenna Assembly P/N is SEG39130674; the Power/Heater cable is P/N SED39129744-301, and the Data/OCA cable is P/N SED39129747-301.) Apparently connector pins and/or screw/bolts were dislodged allowing the connector(s) to emit part(s). The proposed solution is to obtain the culprit cables (power and data) of the returned EComm Starboard Antenna and provide an evaluation and analysis to determine the condition of the cables and connectors, and the likely cause(s) for the connector part(s) coming loose. This IFI can be closed because EComm is GFE, a PRACA should be written to track this issue. The problem is likely a design, manufacturing, or readiness for flight issue. Since the EComm is has been de-commisioned on 6A, the connector design or manufacturing issues are moot. No future use of the EComm is planned for ISS/Station.(Recommend that this IFI be closed via FIAR # ______.) Awaiting return of data and power cables to determine parts missing and to assess cause.



  • C&T – (MER-0400) — Regul Acquisition of Signal Error

Working with Russians / MER Moscow. This IFI Under Investigation.



  • C&T — (MER-0421) – Ku Band PLC to Normal in Mask

As reported by CATO, a “Ku-Band Radiating Beyond Mask” warning was annunciated at GMT 2001/156:18:27:30. As expected the Ku-Band TRC was powered OFF. CATO RTPLOT indicates that TRC PLC went to “Normal” at 156:18:27:31. The Ku-Band PWRL was at -57 dBm when the PLC went to “Normal”. The TRC Xmit Output voltage was at 0 volts (therefore, we did not radiate within the protected Mask. CATO performed CAFN576, Ku-Band Radiating Beyond Mask Corrective Actions, in order to recover the Ku-Band TRC. Investigation continues.



  • C&T — (MER-0425) – Ku-band PLC Reset

A TD171 to TD171 Single Access handover occurred at GMT 2001/163:09:26:47. Prior to the handover, the Ku-Band system was operating nominally in autotrack mode. After the handover back to TD171 at 163:09:27:07, a TRC Execute function Configuration command was sent at 163:09:28:06 to configure the Ku-Band back to autotrack mode. The command was accepted and the system transitioned to open loop slew then began the spiral acquisition sequence as expected. The TD171 fwd link signal was found during the spiral search and the system transitioned to acquisition lock state with a PWRL of —47 dB, The PLC state transitioned from reset to normal momentarily, but then transitioned back to reset. As a result, the Ku-Band transmitter output power remained at zero. The Ku-Band Antenna was neither near a mask nor did the PWRL value drop below —51 dB at any time after the initial acquisition sequence. The system remained in autotrack mode and continued to track the TD171 FWD link until the end of the TDRS event at 163:09:33:57. The Ku-Band PWRL level remained at a level of —46dB and PLC state remained in reset for the entire event. When the TDRS handover began the TDRS signal strength dropped below the CCS monitored threshold so the C&C MDM commanded the antenna to Pointing Mode Inhibit and PLC to Reset as part of the “Drop Lock” CCS patch. When the handover was complete the CATOs commanded the antenna back to Autotrack, and the antenna successfully locked to the TDRS signal. When the antenna declared lock to the TDRS signal the TRC firmware put the PLC in Normal. At this same time the C&C MDM commanded the antenna back to Pointing Mode Autotrack as part of the CCS “Drop Lock” patch. As a side effect of this command the PLC was taken back to Reset.

Any time the Ku-band losses the TDRS signal, the C&C MDM is going to declare “loss of lock”. Two minutes later, regardless of the state of the antenna, the C&C MDM is going to command the Pointing Mode back to Autotrack. The last CCS commanded state of the PLC will also be included in this command. Every time the Ku-band antenna losses the TDRS signal, the C&C MDM will command it back into Autotrack after two minutes. This command will also include the last state of the PLC which should be Reset when we are in Autotrack. After short (<1 minute) TDRS handovers let the CCS software command the Ku-band antenna back into Autotrack. Investigation continues.



  • C&T — (MER-0434) – Spare SASA RT Conflict

Under Investigation.



 


THERMAL CONTROL GROUP (TCG)



  • TCS — (MER-0403) – Ammonia Contamination of Lab ITCS Fluid

Samples of ITCS fluid were removed from the two operating ITCS loops during flights 5A, 5A.1, and 6A and returned to ground for analysis. The 5A samples showed no ammonia contamination. The 5A.1 samples had an ammonia concentration of 0.03 to 0.05 ppm (estimated due to this level being at the boundary of the detectable limit) in the low temperature (LTL), and the moderate temperature loop (MTL) was 0.09 ppm. The 6A samples have a 0.096 ppm, MTL; and a 0.142 ppm, LTL. The concern is that the trace amounts of ammonia contamination are being introduced to the fluid streams by a “micro-crack” or fissure within the single barrier interface heat exchanger (IHX). A “micro-leak” is not a catastrophic hazard to the crew. Threats to the hardware ( both internal and external) are unknown at this time. Once all possible sources of ammonia contamination are investigated, and if it is determined that the ammonia contamination is from an IHX, then the deficient heat exchanger will need to be removed and replaced by EVA operations. Presently, a spare IHX is stored in the USL. Procedures will have to be developed to remove and replace the IHX. Ammonia contamination in the ITCS fluid could come from: 1) sample bag material/contamination; 2) cabin atmosphere; 3) ground laboratory processing; 4) microbial activity; and/or 5) interface heat exchanger “micro-leak”. A team of engineers/scientists has been formed under the leadership of Cynthia Cross (JSC-EC) and Steve Daugherty (Boeing Active Thermal Control Team). The team consists of representatives from System Safety, Materials & Processes, and Engineering, with specialists in fracture control, chemistry, and fluid hydraulics. A detailed plan is being formulated to investigate potential sources of ammonia contamination. Samples will be taken and returned to ground for analysis at 7A and 7A.1 for trend analysis. It is noted that the quantities of ammonia contamination are “trace” amounts. The ITCS soft materials were tested at an 8.87% ammonia solution by weight ( Reference: Test Report Nonmetallic Material Compatibility with Ammonia , issued by Materials and processes laboratory, Marshall Space Flight Center, date: 10/96) for time periods of 30 and 60 days with all materials in contact with the ITCS fluid showing no significant degradation. 05/30/01: JSC is currently investigating (designing and funding) a test with ITCS fluid in a FEP sample bag to confirm the adequacy of the bag material in preventing ammonia from being absorbed from the cabin atmosphere. Investigation Continues.



  • TCS — (MER-0411) — ESP Survival Heaters Off Since 6A

Power was removed from the ESP-1 secondary heaters at 2001/116:15:51 and they were left off until it was discovered on day 147. ESP-1 houses a spare PFCS and a spare DSCU. During flight 6A, NCS control was lost and RACU 6 was power cycled at 2001/116:15:51 to remove and reapply power to the N1-1 MDM in an attempt to regain NCS control. The RACU 6 power cycle caused power bus N1RS1 and all its loads to lose power. The 6A N1RS1 Power Bus Repower procedure was missing the ESP heater load on RPCM N1RS1-B RPC 4. Consequently, the ESP-1 secondary heaters were left off until it was discovered on day 147. Also during flight 6A, due to bad NCS data, the DDCU Z1-3B had an NCS software initiated trip at 2001/117:02:13. This caused power to be removed from power buses N13B and N1RS2 and all their loads. The 6A N13B Power Bus Repower procedure was missing the ESP heater load on RPCM N13B-A RPC 3. Consequently, the ESP primary heaters were left off unti

SpaceRef staff editor.