Status Report

Space Shuttle Processing Status 17 May 2001

By SpaceRef Editor
May 17, 2001
Filed under , ,

MISSION: STS-104 – 10th ISS Flight (7A) – Airlock

VEHICLE: Atlantis/OV-104

LOCATION: Orbiter Processing Facility (OPF) bay 3

TARGET KSC LAUNCH DATE/TIME: NET June 14, 2001 at 4:11 p.m. EDT

TARGET KSC LANDING DATE/TIME: June 25, 2001 at 11:51 a.m.

MISSION DURATION: 10 days, 19 hours and 40 minutes

CREW: Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Orbiter close-outs continue in preparation for
Atlantis’ transfer to the Vehicle Assembly Building. However, additional
work on the orbiter’s external tank door has slipped that transfer to
Tuesday, May 22. An environmental seal and metal mounting strip on the
left-hand door were replaced yesterday and door cycling tests are being
conducted Saturday. Managers do not anticipate an impact to the June 14
target launch date at this time.

Technicians have completed integrated hydraulic and flight control checks.
Landing gear functional tests are also complete. This week workers will
perform routine structural leak checks in the orbiter’s aft and midbody
compartments.

Upcoming Milestones (dates are targets only):

Orbiter transfer to VAB – May 22

Space Shuttle rolls out to Launch Pad 39B – May
27

Flight Readiness Review – May 31

Terminal Countdown Demonstration Test complete – June 1

MISSION: STS-105 – 11th ISS Flight (7A.1) – Leonardo MPLM

VEHICLE: Discovery/OV-103

LOCATION: OPF bay 2

TARGET KSC LAUNCH DATE/TIME: July 12, 2001 at 4:45 a.m. EDT

TARGET KSC LANDING DATE/TIME: July 23, 2001

MISSION DURATION: 11 days

CREW: Horowitz, Sturckow, Barry, Forrester; (ISS up) Culbertson, Dezhurov,
Turin; (ISS down) Usachev, Voss, Helms,

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Discovery’s payload premate test is complete.
Checks on the orbiter’s water spray boilers and main propulsion are ongoing.
Servicing of Discovery’s potable water system is under way as well.

MISSION: STS-108 – 12th ISS Flight (UF1) – MPLM

VEHICLE: Endeavour/OV-105

LOCATION: Orbiter Processing Facility bay 1

TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001

TARGET KSC LANDING DATE/TIME: Dec. 9, 2001

MISSION DURATION: 10 days

CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS
down) Culbertson, Dezhurov, Turin

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Technicians have completed Endeavour’s Ku-band
antenna system checks. Postflight inspections of the orbiter’s main engines
and main propulsion system are in progress today. Forward reaction control
system checks are scheduled to occur this week.

MISSION: STS-109 – HST Servicing Mission 3B

VEHICLE: Columbia/OV-102

LOCATION: Vehicle Assembly Building high bay 4

TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002

TARGET KSC LANDING DATE/TIME: Jan. 28, 2002

MISSION DURATION: TBD

CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino

ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees

Shuttle Processing Note: Columbia is being stored in VAB high bay 4 until
Atlantis moves to the VAB to be mated to the STS-104 external tank and solid
rocket boosters. Columbia will then be transferred into OPF bay 3 to
continue STS-109 preflight processing.

SpaceRef staff editor.