Status Report

EVA Hardware Board (EHB) Minutes of Meeting May 2, 2001

By SpaceRef Editor
May 2, 2001
Filed under , ,

The EHB met at JSC on May 2, 2001, in Building 1, Room 360, at 1:00 p.m. Representatives from the following organizations participated:

EVA Project Office

Hardware Development

Integration and Operations

Astronaut Office

Engineering Directorate

Crew & Thermal Systems Division

EVA and Spacesuit Systems

EVA, Robotics, & Crew Systems

SR&QA

FCE/EVA

Hamilton Sundstrand Windsor Locks (HSWL) via telecon

Hamilton Sundstrand Management Services

USA

Lockheed

EHB Board members from the following organizations participated:

XA/Chairman, XA/Secretary, XA/Tools and Crew Aids, XA/EMU, XA/Integration and Operations, CB/Astronaut Office, DX32/EVA Task Group, EA/Engineering, EC5/EVA GFE, MV5/FCE, and NA/SR&QA.

The following items were presented:

1. Hardware Integration Schedule – XA/Barbara Counts

Changes to the schedule include STS-110 (8A) CEIT ship 11/7/01, Payload Bay Ship 11/16/01, CEIT 11/16/01, and Bench Review 12/7/01.

2. Discussion Item: CETA Cart/MT Energy Absorber Redesign – XA/Dale Roberts

Funds for CCBD H-0980 for the CETA Cart/MT Energy Absorber Redesign have been transferred to EC5; however, the CCBD still requires additional wording from EC5 before signature. EC5 was requested to incorporate any changes and forward for signature by 5/4/01.

3. Discussion Item: CARD Changes – XA/Dale Roberts

Requirements to update the On-Orbit Installed Handrail Carrier CARD, JSC-38721 were authorized over a year ago. The CARD update was initiated 4/26/01 and approved 5/1/01. Bench Review for STS-104 (7A) is 5/15/01. Mr. Roberts requested that in the future all CARD updates be handled in a more timely manner to avoid last-minute deliveries.

4. Walk-on: H-0826R2 – Crew Hook Lock Retrofit – R2: Make Addition of Lanyard to Crew Hook Lock and ERCM Tether Standard for PLB-Stowed ERCM – XA/L. Crocker

This CCBD requests making the integrated Crew Hook Lock, Lanyard, and ERCM Tether the standard configuration for the Payload Bay stowed tethers for flights beginning with STS-104, until crew hook redesign has been implemented. It requires an update to the tech order and post-7A Standard ESEL.

Decision: Hold pending further discussion.

5. Discussion Item: EMU Items – XA/Brian Johnson

The EMU Technical Manager reported that three CCBD’s are being revised to update flight effectivity They are:

H7148R1 – EMU SSA Waive Phase VI Thermal Glove Curves for STS-100 (6A), STS-104 (7A) and STS-110 (8A), excluding STS-106 (2A.2b)

H7152R1 – EMU Waiver for PLSS 02 Temperature for STS-100 (6A) and STS-104 (7A) through
STS-121 (13A.1), excluding STS-106 (2A.2b)

H7153R1 – EMU Waiver EMU EMI Requirements for STS-100 (6A), STS-104 (7A) and STS-105 (7A.1)

These CCBD’s will be routed OSB.

6. PRACA Status – NS43/Terry Miller

Eleven FIAR’s are open for EVA hardware and are shown by flight as follows:

STS-104 (7A) 2

STS-105 (7A.1) 8

STS-109 (HST) 11

STS-108 (UF1) 10

Three FIAR’s were reported past due. Status was given on the following:

JSCEC0863 – Modular Gimbal Assy. End effector is sticking/not closing (STS-98 anomaly).

This FIAR will be discussed off-line.

JSCEC0851 – General Purpose Cutter (GPC). GPC handle does not lock with torque spec of 10-40 in/lbs., measured 6.6 in/lbs.

EC5 will do interim. Lockheed is redesigning, building piece-parts. New ECD is 5/30/01. XA/EC need to tag-up to go over new design.

No new FIAR’s were reported.

The following STS-104 (7A) FIAR was statused:

JSCEC0839 – REBA Charger. REBA failed to show green LED during acceptance testing.

EC5/Roger Schwarz reported that the SSM (Hiep Nguyen) is in route to the vendor this date to get root cause of the failure. An interim will be written for 7A.

The following STS-105 (7A.1) FIAR’s were statused:

BFCE029F105 – Pistol Grip Tool (PGT). PGT Chatter.

This FIAR is pending input from the SSM/Gary Nickel.

JSCEC0867 – High Strength Bridge Clamp. Damaged EVA locking pin on High Strength Bridge Clamp Assy.

This hardware is with EM for further analysis.

The following SAFER FIAR for STS-105 was statused:

JSCER0035 – USA SAFER. SAFER battery erratic current readings.

NC/Ron Cook reported that the interim was signed Monday, 4/30/01.

The oldest FIAR, against the Adaptive Payload Carrier, is 603 days old.

3. On-Orbit Limited Life Status – NA/Rod Toler

The On-Orbit Limited Life Status is scheduled for presentation on the 2nd and 4th Wednesday.

4. Certification Status – NS22/Greg Wright

There are 17 hardware certification items open for STS-104 (7A). There are 9 open hardware certifications for STS-105 (7A.1). There are 9 open hardware certifications for STS-109.

5. EMU RDR and Certification Status – NC512/Charles Sager

EMU RDR’s open by flight are as follows:

STS-104 (7A) 5

STS-105 (7A.1) 7

STS-108 (UF1) 13

STS-104 (7A) RDR’s were statused as follows:

B-EMU-104-F002 – Boot Fit.

Still working issue. Have incorporated Parazynski inputs.

B-EMU-105-F001 – Eye Irritation.

Crew not available until 5/10/01. Will bring interim to 5/3/01 call.

B-FCE-021-F002 – Loss of power indication on Middeck Battery Charger.

Final expected 5/3/01.

All RDR’s for STS-105 (7A.1) are within the CoFR2 date of 6/12/01.

STS-108 (UF1) RDR’s were statused as follows:

H-EMU-000-001 – SOP NVR Contamination.

A meeting has been scheduled for 5/10/01 to review this item.

H-EMU-123-011 – Plug separating fluid circuits is loose – F/P/S.

CLOSED.

JMETOX111A001 – Regenerator oven solenoid did not actuate canister state indicator.

This item will be rescheduled, as it did not make the 5/1/01 call.

There are 26 open certification items for STS-104 (7A), most require simple paperwork to close out by CoFR2. There are 4 open certification items for STS-105 (7A.1). There is no open certification to report for STS-108 (UF1).

6. STS-104 (7A) Open Paper – XA/Brian Johnson

A list of open documentation and dates for expected closure on STS-104 (7A) items was presented.
This list included ESEL, ILCVR, fingertip protection, battery, BTA, GFE, and RDR/IFA items. Also included was the EMU consumables EMUM, ISS Procedures Review and EVA PCU Safety items.

7. Funds Transfer Status – XA/Janice Hall

Funds transferred this reporting period are as follows:

EMI/EMC Testing on the EMU Glove Heater Assembly $3,500

EVA Tool Block Buy #1 $900,000

8. IFA Status – XA/Greg LeStourgeon

This item was deferred. The Secretary requested that the IFA list be reviewed. One new IFA for STS-100 (6A) was added. Pending IFA’s for STS-92 (3A), STS-97 (4A), STS-98 (5A), and STS-102 (5A.1) were included.

9. EMU Rotation Plan – HSWL/Donna Ray

Any changes to the EMU Rotation Plan will be presented the last Wednesday of the month.

9. USA SAFER Flight Logistics Plan – XA/Anh Huynh

Any changes to the USA Safer Flight Logistics Plan will be presented the last Wednesday of the month.

10. EHB Action Status – XA/Greg LeStourgeon

This item was deferred.

11. H7147 – EMU SSA Fabrication of Phase VI Glove Dual Seal Wrist Bearings – ILC/T. Munro

This item was deferred.

12. H-0984 – Extend Launch/Landing Constraint for High Strength Bridge Clamp and Push Button Articulating Socket – XA/Kristin O’Brien

This CCBD requests performing necessary dye pen inspection and vibration testing on HSBC P/N SED33107177-301, and PBAS, P/N SED33105422, to verify analysis to extend launch/landing limit to 96 launch/landings.

Decision: Approve.

13. Gold Salt Hydrazine Detection Kit – EC3/John Graf

This presentation outlined the progress to date for an ISS airlock contamination detector kit. It was reported that approximately 40 Shuttle gold salt samplers and the Shuttle color reference cards are ready for ISS use. A new sample hose assembly is in fabrication and a prototype should be ready by the next SSATA test (5/9/01). This is being proposed instead of the hand-held sample pump and associated PGT adapter proposed 2/26/01. The kit stowage bag will not be ready for 7A. It was suggested that the samplers be stowed in the staging bag for 7A, which contains several pouches. Two adapters, 18 sample holders, and 2 reference cards need to be added to the ESEL.

This proposal has already been taken to the SMART as an informational briefing. The prototype hose assembly is scheduled for delivery 5/11/01, Bench Review is 5/15/01, and CDR is 5/16/01. GCAR is expected to be complete and hydrazine measurement hardware ready to ship on 5/25/01.

Direction is still required on the Draeger tubes recertification. USA is working N204 Draeger tubes certification.

No further items were brought forward, and the EHB adjourned.

Submitted by:

(Original signed by)

___________________________

Harriett Attaway

EHB Secretary

Approved by:

(Original signed by)

____________________________

Greg LeStourgeon

EHB Chairman

SpaceRef staff editor.