Status Report

EVA Tools and Crew Aids Panel Minutes of Meeting 26 Mar 2001

By SpaceRef Editor
March 26, 2001
Filed under ,

The EVA Tools and Crew Aids Panel met at JSC on March 1226, 2001, in Building 1, Room 360, at 1:00 p.m. Representatives from the following organizations participated:

EVA Project Office


Hardware Development


Integration and Operations


Engineering Directorate


Crew and Thermal Systems Division


FCE EVA


Safety, Reliability and Quality Assurance Office


Hamilton Standard Management Services


Lockheed Martin



Panel members from the following organizations participated:

XA/Panel Chair, XA/Panel Secretary, XA Integration and Operations, CB/Astronaut Office, DX3/EVA, Robotics, and Crew Systems Operation Division, CB/Astronaut Office, EC5/Crew and Thermal Systems Division, FCE/EVA, and NA/SR&QA.

The following items were presented:

 


  1. PRACA Status — NS43NS43/G. WrightT. Miller

Fifteen Sixteen FIAR’s are open for EVA hardware. Four One FIAR’s were was reported as past due and statused as follows:

BFCE026F005 — Disk/Loop Pin Puller Tool Caddy. Broken Tether cord.

This FIAR will be statused at the 3/28/01 EHB.


JSCEC0848F — Equipment Hook. Inadvertent Equipment Hook release.

PIA’s in work on everything with hook.

JSCEC0849F — Safety Tether. Slow retract of tether.


To do ROM to reduce length of tether. Once ROM received and crew/MOD concurs, FIAR can be closed. Unless found to be an overriding safety concern, no plans for mod or redesign.


JSCEC0841 — PFR Gimbal Assembly. Roll joint buttons binding.


Possible processing problem with dry lube application.


JSCEC0852 — Equipment Hook. Bail level sticking. Bail level did ot perform smoothly and did not stick open.

New build failed initial PIA.

One No new FIAR’s was were reported. No FIAR’s are open for STS-100 (6A).

The following STS-104 (7A) FIAR was statused:


CLOSED.

 


 


 


JSCEC0842 — Modular MWS Gimbal Assy. Fraying of end effector cord.

Closure in final signature loop.

 


 


Preliminary closure in work. Still had chatter on 5A. Look at closing "as is".

EC5/B. Greene presented a FIAR Status on JSCEC0853F — Bayonet Receptacle.


STS-92 and STS-98 crew experienced excessive loads required to remove hardware from Bayonet Receptacles on the Modular Mini-workstation T-Bar and Swing Arms.

 


 

The following STS-104 FIAR’s were statused:

JSCEC0839 — REBA Charger. REBA failed to show green LED during acceptance testing.

Going to vendor end of March to get root cause closure.


JSCEC0841 — PFR Gimbal Assembly. Roll joint buttons binding.

Need to get with EM for root cause.

JSCEC0842 — Modular MWS Gimbal Assy. Fraying of end effector cord.

In work. Cost substantial.

JSCEC0781F — 5/16" Wobble Socket (HST). Socket detaching from PGT during STS-103 EVA.

Funded. Design change complete. Close out.

JSCEC0848F — Equipment Hook. Inadvertent equipment hook release.

Should have final by next week.

JSCEC0850 — Safety Tether. Discoloration of safety tether.

Test results by 3/19/01.

The following STS-104 SAFER FIAR was statused:

JSCER0035 — USA SAFER. SAFER battery erratic current readings.

Currently on-orbit. Will not get back until 6A lands. Will need month to do assessment.

The EVA hardware oldest FIAR, opened against the Adaptive Payload Carrier, is 547 568 days old.

FIAR’s open by flight:

STS-102 0


STS-100 (6A) 20


STS-104 (7A) 1010


STS-105 (7A.1) 1315

 


  1. Cert Status — NC52/G. Wright

All certification is closed for STS-102.

There are three open SAFER hardware certifications for STS-100 — 2 on the SAFER IVA Battery (-305 and -307), and SAFER Battery upgrade. These are pending GCAR updates for closure.

There are 22 open hardware certifications for STS-104, all "green".All hardware certifications are closed for STS-100 (6A). There are 20 open hardware certifications for


STS-104 (7A). There are no open hardware certifications for STS-105 (7A.1).

 


 


 


 


  1. Mission Hardware Status — LM/F. BlissK. Thomas
  2. The following Mission Hardware Status was presented:



    STS-102: All hardware has been delivered for flight.

    STS-100: STS-98 hardware was received from USA on 3/2/01, and is being processed for the STS-100 Bench Review on 3/16/01. Roughly 20% of Bench Review hardware has been shipped. The other hardware will be sent as it is processed.

    STS-104: All hardware was delivered to support the Airlock Bench Review, scheduled for 3/2/01.STS-100

    Hardware processing is in work for the MMWS RH Swingarms, Camera Bracket Assy, and REBA and EHIP hardware. All hardware should be available to ship to USA on or before 4/3/01.

    STS-104

    Hardware is being processed for the STS-104 Payload Bay Ship, scheduled for 4/3/021. Waiting for one Sill Stack to return from STS-102 that should be here on 3/28/01 at the earliest. The PFR and High Strength Bridge Clamp are needed.

    STS-105

    Work has begun on processing hardware for the STS-105 MPLM Bench Review, scheduled for 4/10/01.

     


     


     


  3. Actions Review — XA/G. LeStourgeonD. Roberts
  4. This item was deferred.

    The following actions were statused:

    Action 1/22/01-1 — EC5/L. Bailey. Provide ROM and assessment of CETA Cart, OTD and TERA grounding patch and any necessary modifications to hardware and present to Tools Panel.

    EC5/R. Schwarz to look into.

    Action 8/28/00-2 — EC5/D. Glebe. Modify drawing for Top Mounted Handrail Assy, etc.

    Per actionee, anticipate meeting 4/8/01 completion date.

    Action 2/5/01-3 — DX3/O. Koehler. Provide details of towel bar installation task to EC5 for review.

    CLOSED per E-mail response of 3/23/01.

    Action 8/28/00-3 — EC5/G. Nickel. Provide plan for materials testing of returned OIH material and update of materials model.

    EC5/R. Schwarz to look into.

    Action 1/29/01-1 — EC5/R. Schwarz. Present findings from testing Load Alleviators and Sheaths.

    Per actionee, all work completed but load test; should get to it this week.

  5. Pending CR Review — XA/G. LeStourgeonD. Roberts
  6. Pending CR’s were reviewed and statused as follows


















































    CCBD #


    Initiator


    Title


    Status


    H-0538R1


    EC5/J. Marmolejo


    Update EVA Batteries to BCA/BSA IDD


    Process


    H-0775R1


    EC5/B. Greene


    ISS TERA Recertification


    On hold


    H-0711


    XA/T. Brady


    Provide 3/126" Allen Drive with Drop Proof Tether Adapter


    On hold


    H-0905


    EC5/L. Bailey


    CETA ICD Fitcheck Verification


    On hold


    H-0870


    XA/T. Jochim


    Ingress Aide Modification


    Disapprove


    H-0843


    DX3/K. Lewis


    USA SAFER Tower latch


    Withdraw


    H-0896


    EV/K. Vorhaben


    Request for Microconical Fittings


    Process OSB


    H-0937


    XA/C. Fulcher


    Orlan SAFER Launch Restraint FSE


    Pending review of XA I&O/TRI


  7. HITS Status Review — XA/J. Manning

 


The weekly "stoplight" HITS Metric Report was presented. This report shows hardware and/or service/support delivered, on schedule, and not meeting planned delivery date or program need date. Open for 6A is the Top-Mounted Passive WIF Assy. Not meeting program need date for 7A is the General Purpose Cutter Replacement Unit. All hardware deliveries are within required dates for 7A.1.


This item was deferred.

  1. Gage Status — EC5/K. Hostetler
  2. This status will not be presented until the monththe first Monday of April.



  3. H-0959 – HST PFR Starboard APC Integration — XA/J. DuttonH-0969 — Evaluate Use of OIH’s While Soft Docked — XA/S. Broussard, DX3/O. Koehler


The APC carrying the HST PFR, PFR extender and jettison handle had to be moved from Port Bay 13 to Starboard Bay 10. This CCBD requests fabrication of a new short shaft, drawing updates, loads models, and building up the starboard configuration to support HST PFR starboard APC integration for STS-109.This CCBD requests using a soft docked OIH as a translation path on STS-104 (7A). It is being proposed to provide additional crew stabilization capability beyond "launched in place" handrails during brief translation to the worksite area.

The Panel was polled and in agreement not to endorse leaving this hardware soft docked.

Decision: Disapprove. MOD to try to find another method for translation.

 


H-0725R2 — Modify Camera Mount Assembly with Equipment Hook — Stop Work — XA/L. Crocker H-0966 — Repackage Nitrogen Dioxide Draeger Tubes — USA/D. Edwards

This CCBD requests changing the Draeger Tube Nitrogen Dioxide packaging from a green foil laminate pouch to a clear bite size package.

This Revision 5 to the STS-100 ESEL contains required configuration updates. No quantity changes are included.

Decision: Route for technical concurrence.

  1. H-0668R7 — Update STS-102 (5A.1) Tools ESEL — XA/A. Mears
  2. This Revision 7 to the STS-102 ESEL contains various serial number updates and deletes the return of SAFER’s and associated hardware.

    Decision: Obtain concurrence of XA/B. Johnson and Route for technical concurrence.

    forward to EHB for approval.


  3. H-858R1 — Update STS-102 Tool-to-Tool Fitcheck Matrix — HSMS/J. Case


  4. This CCBD updates the STS-102 Tool-to-Tool Fitcheck Matrix to reflect the STS-102 Rev 7 Tools ESEL.



    Decision: Route for technical concurrence.

     


     


     


     


  5. H-0960 — STS-102 Open Tool-to-Tool Fitchecks — HSMS/J. Case

This CCBD requests EHB concurrence on accepting the risk of not performing all tool-to-tool fitchecks for STS-102. Root cause of the inability to complete the fitchecks is late addition of tools to the flight, new hardware builds, and hardware logistics disconnects and planned operational use. Fitcheck status was presented to the STS-102 EVA FRR, held 2/27/01. In the future, all fitcheck status is to be documented prior to FRR.

Decision: Forward to 3/7/01 EHB.

  1. Extension of USA SAFER Sliders — ER/K. Lewis

Background: Due to the design of the Small EMU and EMU Planar HUT, some crewmembers may be unable to operate the manual isolation valve or deploy the HCM to initiate a self-rescue without extending the sliders forward.

This presentation is in response to action requirements contained in H-0906 – Extension of USA SAFER Sliders. The action called for ER to provide cost and schedule estimates for the following:


  • Developing a viable design concept for moving the SAFER slider mechanisms forward 2 inches.

  • Developing the detailed design, fabrication, and certification plan for the new concept.

  • Retrofitting the Class I SAFER fleet and the Class III SAFER Engineering Unit with the modifications.

  • Updating the required documents as appropriate.

A review of the SAFER drawing list has identified 49 drawings that will require modification or replacement to implement the change, with a possibility of more being identified during the design process. The structural redesign will require new stress and thermal analyses and a repeat of development and certification test programs.

Several issues were also brought forward. Modifications will require change of HCM deployment, causing SAFER to violate PRD stowed volume requirements, increasing weight, and increasing risk of inadvertent HCM deployment and Manual Nitrogen Isolation Valve closure.

At the ROM estimate of $4.130K, and the 2.5 years required to build and certify, ER has recommended not implementing this change.

CB/C. Nicollier requested data on reach evaluations and further evaluation or existing spreadsheet on length of time taken to reach sliders. The chairman suggested ER provide (to the EHB) the data on the negative loads margin due to the extension of the sliders.

Decision: Forward to 3/7/01 EHB.

 


 


No further items were submitted and the Tools Panel adjourned.

 


 


Submitted by: Approved by:

(Original signed by) (Original signed by)


________________________________ ________________________________


Harriett A. Attaway D. G. LeStourgeonDale R. Roberts


EVA Tools & Crew Aids Panel Secretary Acting EVA Tools & Crew Aids Panel Chairman

 


Note: CARD changes are normally routed for concurrence after the Panel adjourns. Initiators are requested to be present or have representation for discussion of the change.

SpaceRef staff editor.