EVA Tools and Crew Aids Panel Minutes of Meeting 12 Feb 2001

By SpaceRef Editor
February 12, 2001
Filed under ,

The EVA Tools and Crew Aids Panel met at JSC on February 12, 2001, in Building 1, Room 360, at 1:00 p.m. Representatives from the following organizations participated:

EVA Project Office


Hardware Development


Engineering Directorate


Crew and Thermal Systems Division


FCE EVA


Safety, Reliability and Quality Assurance Office


Hamilton Standard Management Services


Lockheed Martin


GSFC

Panel members from the following organizations participated:

XA/Panel Chair, XA/Panel Secretary, CB/Astronaut Office, EC5/Crew and Thermal Systems Division, NA/SR&QA, and USA FCE/EVA.

The following items were presented:

 


  1. PRACA Status — NS43/T. Miller

Seventeen FIAR’s are open for EVA hardware. Four FIAR’s were reported as past due and statused as follows:

JSCEC0796 — Active WIF Assy. Active WIF Control Knob appeared to have increased force to operate.

Final in XA signature loop.

JSCER0033 — USA SAFER. NSI trace on oscilloscope appeared abnormal.


Closure in work. CR H-0949, Change to USA SAFER NSI Self Test Specification, approved. Per NA/R. Cook, closure is pending MOD action to change SAFER IVA checkout and training procedures.

The following EHB action was assigned:

Action 2/12/01-1: Modify SAFER IVA checkout and training procedures to incorporate opening manual isolation valve during SAFER self test.


Actionee: DX3/R. McDaniel


Due Date: 2/28/00


JSCEC0839 — REBA Charger. REBA failed to show green LED during acceptance testing.


Investigation is ongoing. No significant information has been obtained. EC5 to give status at the next EHB.


JSCEC0846 — APFR. Rotation of collar is difficult/sticking.


Hardware inspected. Probably not design problem but manufacturing error on unit. EC5 to present plan and options at the next EHB.

 


 


 

One new FIAR was reported:

JSCEC0853F — Bayonet Probe. Crewmember from STS-92 experienced unsatisfactory fit of bayonet probes to bayonet receptacles.

EC5 to bring plan and options to 2/21/01 EHB.

The EVA hardware oldest FIAR, opened against the Adaptive Payload Carrier, is 526 days old.

FIAR’s open by flight:

STS-102 1


STS-100 3


STS-104 12


STS-105 15

  1. Cert Status — NC52/G. Wright

There are two open hardware certifications for STS-102 — EVA Scissors, and QD Cap Removal Tool. The cert unit on the scissors is coming back to USA. An ESEL revision is in work to delete the QD Cap Removal Tool.

There are three open hardware certifications for STS-100 — 11/16" Box End Wrench, Portable Foot Restraint Attachment Device (PAD), and Equipment Tether Reel.

There are 21 open hardware certifications for STS-104, all "green".

  1. Mission Hardware Status — LM/F. Bliss
  2. The following Mission Hardware Status was presented:



    STS-102: All hardware that was returned from Bench Review should be back at USA on 2/14/01. Flight ship from USA to KSC is 2/20/01.



    STS-100: Currently waiting on hardware to come back from TSA pull test to be processed for payload bay CEIT shipment. Currently trying to locate a 2" socket. The GP Cutter Handles are going through thermal tests today and should have test results later this evening. XA/R. Fair reported that the PFR PIA cannot be completed due to a lack of gages. EC5/K. Hostetler reported that gages should be available tomorrow. The 11/16" Box End Wrench is late, but this was expected. Payload bay/CEIT shipment is scheduled for 2/16/01 and the CEIT is currently scheduled for 2/24/01.

    STS-104: All hardware should be delivered to support Airlock Bench Review, scheduled for 2/27/01.


  3. Actions Review — XA/D. Roberts
  4. This item was deferred.


  5. Pending CR Review — XA/D. Roberts
  6. This item was deferred.


  7. HITS Status Review — XA/J. Manning

The weekly "stoplight" HITS Metric Report was presented. This report shows hardware and/or service/support delivered, on schedule, and not meeting planned delivery date or program need date.

 


  1. Gage Status — EC5/K. Hostetler
  2. The monthly Gage Status was presented. This status shows ages that will expire, gages that are in for calibration, gages that are not in for calibration, and new gages and gages in calibration.



  3. H-0946 — Baseline STS-104 (7A) Tool-to-Tool Fitcheck Matrix — HSMS/J. Case

This CCBD baselines the STS-104 Tool-to-Tool Fitcheck Matrix based on the STS-104 Rev. 3 Tools ESEL.

Decision: Route for technical concurrence.

  1. H-0752R2 — Modify Camera Mount Assembly with Equipment Hook — Stop Work — USA/V. Myers

This CCBD requests a "stop work" on modifying the Camera Mount Assembly by replacing French Hooks with Equipment Hooks as outlined in H-0752R1. Revision 1 authorized the modification of 12 Class I and 8 Class III Camera Mount Assemblies. To date, three units have been completed. No clear crew consensus on preference for old-style camera mounts versus new camera mounts has been established. CB/C. Nicollier will forward this issue to CB Management. XA will also hold internal discussions on this issue.



Decision: Hold pending outcome of CB and XA consensus and forward to EHB.

  1. H-0862R1 — Revise Russian Launch ESEL for progress 3P — XA/C. Fulcher
  2. This item was deferred to the next Tools Panel.

  3. Walk-on: HST Crew Fam & Fitchecks — HSMS/W. Parker


A crew fam and fitchecks for HST (STS-109) hardware has been requested by GSFC/S. Butler and XA/B. Counts. Approximately 85 Class I items have been identified. Per the Chairman, tool-to-interface fitchecks are acceptable, but what the hardware is being interfaced with needs to be identified. The 3B fitchecks will not be repeated. HSMS/J. Case, the STS-109 fitcheck Lead, will present requirements to XA off-line.

Decision: Before hardware is sent, provide adequate justification/rationale for each tool to be shipped to Panel Chairman.

 


 


No further items were submitted and the Tools Panel adjourned.

 


 


Submitted by: Approved by:

(Original signed by) (Original signed by)

________________________________ ________________________________


Harriett A. Attaway Dale R. Roberts


EVA Tools & Crew Aids Panel Secretary EVA Tools & Crew Aids Panel Chairman

 


Note: CARD changes are normally routed for concurrence after the Panel adjourns. Initiators are requested to be present or have representation for discussion of the change.