Accomplishments & Activities

Since December Quarterly Review

  • Budget:


    • Have agreed upon cost marks for Node 3 regenerative ECLSS & Sustaining Engineering test
      bed activities.
    • Working to achieve requested additional cost reduction in FY01 for regenerative ECLSS.
    • Work force reductions proceeding according to plan.
    • Reworking schedules for 12 month delivery slide; will request formal schedule rebaselining at
      March 21 Quarterly Review. Detailed proposal due from Hamilton Sundstrand by April 2.
    • Working Building 4755 & 4708 facilities consolidation action with Boeing.


  • VCD Flight Experiment:


    • Completed In- [SpaceHab] Module Integrated Verification Testing on 12/15/00.
    • Acoustics noise deemed unacceptable by SpaceHab during module testing. Spacehab had
      previously accepted hardware delivery & installation into module knowing acoustics data.
    • Bisco wrap added to Distillation Assembly (primary noise driver).
    • Evaluating additional options including DA bearing replacement, rack level attenuation, reduced
      operations on-orbit with crew present in module.


  • Integrated Racks & Urine Processor:


    • Completed Interim Project Review on 12/14/00.
    • Reviewed On- Orbit ORU changeout design with Astronaut Office & MOD on 1/17/01.

    • Meeting with Hamilton Sundstrand to finalize open interface TBDs & remaining O2 generator
      design concerns.

    • Urine Processor condensate- in- bowl heater testing & bearing/ seal plan proceeding on schedule.