NASA ISS On-Orbit Status 15 May 2013

By SpaceRef Editor
May 15, 2013
Filed under , , ,
NASA ISS On-Orbit Status 15 May 2013
NASA ISS On-Orbit Status 15 May 2013

International Space Station (ISS) Management Center (IMC) Daily Summary Report
Increment 35 Operations – Stage 35-6
05/13/13 10:30 pm Central Daylight Time (CDT)
134 3:30 Greenwich Mean Time (GMT)
Tuesday 05/14/13 is a Crew Day Off and no reports will be sent. ISS Daily Summary Reports will resume on Wednesday 05/15/13.

New Status: Change of Command: On Sunday, off-going ISS Commander (CDR) Chris Hadfield handed ISS command responsibilities over to CDR Pavel Vinogradov, making the 34 Soyuz (S) crew the prime crew in the event of an ISS emergency.

33 Soyuz (S) Cargo Return and Undock Preparations: FE-6 Marshburn collected and packed Japan Aerospace Exploration Agency (JAXA) area dosimeters for return on 33S. The EMU gloves and communication cap that were used on Saturday for the USOS EVA were also packed for return, as well as the late load items. The 33S crew (Hadfield, Romanenko and Marshburn) completed preparations for undock.

33S Landing: Soyuz 33S (TMA-07M, #704A) undocked from the International Space Station (ISS), Russian Segment (RS) Multi-purpose Research Module 1 (MRM1) Nadir docking port at GMT 133/23:07:54 (5:07 pm CDT). Prior to the undocking, the crew performed leaks checks of the vestibule area between the MRM1 docking port and the Soyuz vehicle, suit leak checks and a leak check of the hatch between the descent module and the habitation module. The undock command, which initiates the opening of the Soyuz vehicle docking hooks, was issued at GMT 133/23:05:00 (6:05 pm CDT). Three minutes after the separation a fifteen second separation burn was performed. The de-orbit burn was initiated at approximately GMT 134/01:37:11 (8:37 pm CDT) and was completed at approximately GMT 134/01:41:56 (8:41 pm CDT) and resulted in an approximately 128 m/sec deceleration. Module separation occurred at approximately GMT 134/02:05:30 (9:05 pm CDT) followed by atmospheric entry at approximately GMT 134/02:08 (9:02 pm CDT). Parachute deployment was scheduled to occur at approximately GMT 134/02:16:20 (9:16 pm CDT). The Soyuz 33S vehicle landed at approximately GMT 134/02:30:52 (9:30 pm CDT) in the nominal (pre-planned) landing zone. The vehicles final landing position was in the horizontal position.

Previous Status (05/09/10):
US Extravehicular Activity (EVA) 21: FE-3 Cassidy and FE-6 Marshburn (EV-1 and EV-2 respectively) performed US EVA 21 today, during which they translated to the P6 truss and removed and inspected the 2B Pump Flow Control System (PFCS). No ice or foreign material was reported and imagery was taken for ground analysis. They then replaced it with a spare from the legacy Early External Thermal Control System (EETCS) system. The failed PFCS was stowed in the spare’s original location. While the crew was still within viewing distance of the area, the newly installed pump was activated. They reported that there was no evidence of leakage. Ground teams are assessing the data from the system. During translation back to the Airlock the crew took the opportunity to relocate an APFR out of the line of sight between the Japanese Experiment Module (JEM) window and the newly installed PFCS. The duration of the EVA was 5:31.

Today’s Planned Tasks
– Internal Audio Subsystem (IAS) Crew Quarters Audio Cable Configuration Prior to ТК 704А Undocking [Complete]
– Perform a soft power cycle on AQM S/N 1003 and AQM S/N 1004 [Complete]
– SAMS Laptop Configuration [Complete]
– On MCC GO Purging Elektron-VM Liquid Unit (БЖ) After Deactivation / r/g 1798 [Complete]
– ТК 704А Stowage Ops / r/g 2152 [Complete]
– Photography of ТК 704А СА Equipment / r/g 2152 p.17 [Complete]
– Setup of GoPro HERO3 cameras in ТПК 704A СА / r/g 2256 step 5 [Complete]
– POLYGEN. Video of fruit flies w/blocked access to food / r/g 2335 [Complete]
– POLYGEN. Closeout Ops / r/g 2334 [Complete]
– POLYGEN. Kit Transfers to ТК / r/g 2334 [Complete]
– Auxiliary Laptop Anti-Virus Update / r/g 1930, 2320 [Complete]
– Treadmill Т2 Monthly Inspection [Complete]
– Encoder Setup in the Lab [Complete]
– ИК0501Gas Analyzer H2О Readings Adjustments. [Complete]
– JAXA-PCG – PCG Hardware Disassembly and Handover to Russian Crew for ТК Packing [Complete]
– ARIL. Case Removal from Thermostat (+4 deg C) and Transfer to ТК / r/g 2332 [Complete]
– BIOEMULSIYA. Removal from thermostat (+4 С) and transfer to ТК / r/g 2331 [Complete]
– CASKAD. Removal of Bioreactor and Transfer to ТК / r/g 2332 [Complete]
– BCAT6 – Stowage [Complete]
– BIF. Removal from thermostatic container and transfer to ТК / r/g 2331 [Complete]
– KRISTALLIZATOR. Joint Packing, Acceptance of PCG kits, Transfer to ТК for Return / r/g 2336 [Complete]
– UBNT – Experiment Session [Complete]
– KRISTALLIZATOR. Photo of PCG Kit Handover from USOS / r/g 2337 [Complete]
– Robotics Work Station (RWS) Teardown [Complete]
– PLAZMIDA. Recomb-K Transfer to СА for return to the ground / r/g 2333 [Complete]
– Removal of Recomb-K from Thermostat and Transfer to ТК / r/g 2333 [Complete]
– Ham Radio Deactivation [Complete]
– Periodic Fitness Evaluation – Nom Ops (subject) [Complete]
– Periodic Fitness Evaluation – Nom Ops (assistance) [Complete]
– ТК 704А Loading Complete Report / r/g 2152, 2165 [Complete]
– Photography of the external surface of ТК 704A СА-БО hatch-manhole / r/g 0284 [Complete]
– Comm config for ТК 704A undocking and descent [Complete]
– USOS Window Shutter Close [Complete]
– Downlink photo of the external surface of ТК 704A СА-БО hatch-manhole and return cargo packing photo [Complete]
– ТК 704А Comm Check via S/G2 [Complete]
– СОЖ Maintenance [Complete]
– Video Camera Assembly adjustment in COL for GEOFLOW-2 experiment [Complete]
– FSL Facility Core Element Lock [Complete]
– Activation of ТК 704А, Removal of ССД301 Light in БО ТК 704А for SM Spares and Comm Check from ТК via S-band / r/g 2360 [Complete]
– Get r/g 2299 from ТК [Complete]
– Stow ССД301 in bag 407-34. [Complete]
– FSL GEOFLOW-2 Experiment Container Removal and Stowage [Complete]
– Setup and Activation of КСПЭ Equipment for Hatch Closure TV coverage from MRM1 / r/g 2356 [Complete]
– Removal and Inspection of Quick-Release Screw Clamps on MRM1 side [Complete]
– ТК-MRM1 Hatch Closure. ISS-MCC-M TV TV coverage of Hatch Closure / r/g 2356 [Complete]
– ISS-MCC-M TV TV coverage of Hatch Closure from MRM1 / r/g 2356 [Complete]
– ТК 704A – MRM1 Hatch Leak Check [Complete]
– P/TV Playback Start [Complete]
– FSL GEOFLOW-2 Experiment Container Removal and Stowage [Complete]
– ECP Video By-pass Connector installation on FSL GEOFLOW-2 EC Panel [Complete]
– Hatch Closure TV Downlink / r/g 2356 [Complete]
– Deactivation of КСПЭ Equipment after Hatch Closure Coverage from MRM1 / r/g 2356 [Complete]
– CASKAD. Removal of Cryogem-03 and TBU S/N 04 / r/g 2338 [Complete]
– ТК 704A ODF Ops; Undocking and Descent Ops [Complete]
– TV downlink showing MRM1 – ТК Interface Before Hatch Closure (Ku-band) [Complete]
– P/TV Playback Stop [Complete]
– Monitor ТК Undocking, ТК docking assembly photos / r/g 2322 [Complete]
– ТК 704А Post-Undocking Comm [Complete]
– On MCC GO Reconfigure MRM1-ТК PEV to CLOSED position [Complete]
– P/TV Playback Start [Complete]
– ISTOCHNIK-M. Preparations for carrying out measurements. / r/g 2330 [Complete]
– ISTOCHNIK-M. Activation of TLM Recording Mode from ТК. / r/g 2330 [Complete]
– ISTOCHNIK-M Closeout Ops / r/g 2330 [Complete]
– Restoring nominal comm config after Soyuz landing

Task List
– 33S US prepack [Complete]
– Data prep return-CDR [Complete]
– Data prep return-FE4
– Data prep return-FE6 [Complete]
– Regen WSTA Fill [Deferred]
– SSC Data Gather [Complete]
– WHC KTO replace
– WHC EDV R&R
– BCATC1 Bubble Photos [Complete]
– HRF Supply Inventory [Complete]
– SSC18 Wired Xtion [Complete]
– ARED Fly Covers
– ARED Slide Tether
– HRM Audit
– COL1D3 Stow Cleanup
– Exercise Rope Audit
– Eye Reference Document Print
– JSL Netgear WAP Stow
– N2 Spare Tools Audit
– D3S Sensor Clean
– Trash D2XS Camera
– IMV Flow Measure
– Training Photo Taking

Ground
– Nominal Commanding [In Work]

Three-Day Look Ahead:
Tuesday, 5/14: Sleep shift, EXPRESS Rack 2 Software load
Wednesday, 5/15: BASS, NH3 Procedure Deploy & Review
Thursday 5/16: BCAT4, Stowage Conference, Water balance

QUICK ISS Status – Environmental Control Group:
Component Status
Elektron – On
Vozdukh – On
[СКВ] 1 – SM Air Conditioner System (“SKV1”) – Off
[СКВ] 2 – SM Air Conditioner System (“SKV2”) – Off
Carbon Dioxide Removal Assembly (CDRA) Lab – Operate
Carbon Dioxide Removal Assembly (CDRA) Node 3 – Standby
Major Constituent Analyzer (MCA) Lab – Off
Major Constituent Analyzer (MCA) Node 3 – Operate
Oxygen Generation Assembly (OGA) – Standby
Urine Processing Assembly (UPA) – Standby