NASA Expendable Launch Vehicle Status Report 11 May 2007
Mission: Dawn
Location: Astrotech Space Operations Facility
Launch Pad: 17-B
Launch Vehicle: Delta II 7925-H
Launch Date: NET June 30, 2007
Launch Time: 15:13:15 p.m. EDT
Mission system performance testing continues and is planned to finish Friday.
A test of the spacecraft’s primary communications antenna is scheduled for May 21.
The spacecraft solar arrays will be attached and deployed May 21 – 24.
The spacecraft will be moved to Astrotech’s Hazardous Processing Facility for fueling on May 26.
Mission: Phoenix
Location: Payload Hazardous Servicing Facility
Launch Pad: 17-A
Launch Vehicle: Delta II 7925
Launch Date: Aug. 3, 2007
Launch Time: 15:35:18 a.m. EDT
Spacecraft spin-balance testing is under way.
The spacecraft will be powered to begin testing on May 14.
The heat shield will be installed on May 15, and a separation test will then be performed.
The spacecraft’s electrical power system will undergo a final performance test on May 17.
The flight software will be loaded aboard the spacecraft on May 21.