SpaceX (SpX)-3 Launch/Berth, Extravehicular Activity (EVA) 26 Status: The ISS Program elected to target April 18th and 19th for SpX launch attempts. Teams are evaluating the following options
– SpX launch on 4/18, berth on 4/20 and EVA 26 on 4/23
– SpX launch on 4/19, EVA 26 on 4/20 and SpX berth on 4/22

Body Measures Investigation: Wakata, with the help of Mastracchio, conducted his Return-30 session of Body Measures. Wakata set up body marker instrumentation and took calibration and body pose pictures along with circumference measurements. He then recorded a neutral body posture video. The goal of this study is to gather data to better understand the magnitude and variability of changes due to microgravity and fluid shifts within the human body during long-duration space flight. Results of the investigation may result in changes to space suit fit and sizing, workstation design, etc. for future missions to maximize performance, prevent injury, and reduce crew time to accommodate their anthropometrics.

EVA 26 Preparations: Flight Engineer (FE)-3 Swanson and FE-5 Mastracchio prepared the equipment lock, Extravehicular Mobility Units (EMUs) and ancillary hardware to support EVA prep activities. Commander (CDR) Wakata, Swanson and Mastracchio performed suit fit checks on EMUs 3005 and 3011 to make any adjustments to suit sizing prior to the EVA.

Today’s Planned Tasks

Laptop RS1(2) Reboot [Complete]
SM ??? (Caution & Warning Panel) Test [Complete]
RSS1,2 Reboot / r/g 1009 [Complete]
Daily Planning Conference (S-band) [Complete]
IFM WHC partial fill [Complete]
Body Measures subject (CDR) [Complete]
Body Measures operator (FE-5) [Complete]
Symbolic Activity / r/g 5390 [Complete]
CMS PFE operator [Complete]
CMS PFE subject [Complete]
EVA equipment lock prep [Complete]
EMU on orbit fit check verification [Complete]
EVA tool config [Complete]
Repack of Repair and Maintenance kits. r/g 5398 [Complete]
MRM2 comm config to support voice comm during the experiment [Complete]
Measuring absolute pressure in Elektron Oxygen Generation Hardware H2 line [Complete]
KULONOVSKIY KRISTALL. Experiment Ops / r/g 5385 [Complete]
Pressurizing Elektron Liquid Unit and Mating ??28-2 Connector r/g 5401 [Complete]
MPEG2 PAO hardware setup in SM / r/g 5307 [Complete]
Restore Nominal Comm Configuration / SM Communications System [Complete]
Crew Prep for PAO [Complete]
TV Conference with Moscow Gymnasium No. 1527 / r/g 5399 [Complete]
Physical Fitness Evaluation (on treadmill). r/g 5389 [Complete]
KULONOVSKIY KRISTALL. Copy and Downlink Data / r/g 5385 [Complete]
Separation of EDV (KOV) [Complete]
MATRYOSHKA-R. Monitoring Lulin-5 readings / r/g 4110 [Complete]
??? Maintenance
55P Transfers and IMS Ops / ??? 427 Cargo Transfers (???) + r/g 5317 [Complete]
IMS Update [Complete]
VIZIR. Experiment Ops. r/g 5396 [Complete]
Audit of Volume behind RS Panels / r/g 5371 (continued) [Complete]
HYBRID battery charge [Complete]
Reaction Self Test (CDR)
Task List

CMS ARED cylinder evac
IFM MDM prep review
IFM MDM gather 2 [Complete]
IFM Sabatier purge [Complete]
WHC KTO Replace
WHC EDV R&R
Roscosmos Report
Uragan Photo
Ekon Photo
ARED RHEOLUBE fix
CSL Client Reload
Gamah seal locate
SODF EVA P&I
ARED SSCV5 pre-gather
CWCI relocate [Complete]
Data prep return
HMS OHA test
KTO EDV audit
MI core return prep
Print WHC MAL card [Complete]
ST-ISS read
Ground

Nominal commanding
Three-Day Look Ahead:

Friday, 04/18: SpX-3 launch, MDM preps for EVA
Saturday, 04/19: Crew off duty, SpX ROBOT training
Sunday, 05/20: SpX-3 berth
QUICK ISS Status – Environmental Control Group:

Component – Status
Elektron – On
Vozdukh – Manual
[???] 1 – SM Air Conditioner System (“SKV1”) – On
[???] 2 – SM Air Conditioner System (“SKV2”) – Off
Carbon Dioxide Removal Assembly (CDRA) Lab – Standby
Carbon Dioxide Removal Assembly (CDRA) Node 3 – Operate
Major Constituent Analyzer (MCA) Lab – Stop
Major Constituent Analyzer (MCA) Node 3 – Operate
Oxygen Generation Assembly (OGA) – Process
Urine Processing Assembly (UPA) – Standby
Trace Contaminant Control System (TCCS) Lab – Off
Trace Contaminant Control System (TCCS) Node 3 – Full up